Required Lead Time Information

Bills of Material lets you automatically compute item, bill of material and routing information required for dynamic lead time offsetting. You can also maintain lead time information manually.

Manufactured Items

Dynamic lead time offsetting uses the following lead time attributes for discretely manufactured items:

Dynamic lead time offsetting uses the following lead time attributes for repetitively manufactured items:

Purchased Items

Dynamic lead time offsetting uses the following lead time attributes:

Routings

When computing manufacturing lead times, operation and resource offsets are automatically assigned to a routing. For material and resource requirement planning, you can optionally include offsets when computing requirement dates.

See Also

Overview of Lead Time Management