Previous  Next          Contents  Index  Navigation  Glossary  Library

Routing-Based RCCP

Routing-based RCCP calculates and compares required capacity to available capacity for the individual resources you assign to operations on your routings. Required and available capacity are stated in hours per week per resource.

Required Hours Calculation

Routing-based RCCP:

The following table shows three master schedule entries for A and illustrates how, for each entry, routing-based RCCP calculates required hours and dates for D1, R2. Remember that during the bill of resource load, Oracle Capacity calculated that 24 hours of D1, R2 is required to build one unit of A, and that setback days for D1, R2 is 3 days. In this example, 10 units of item A are required on 07-FEB. Routing-based RCCP calculates the required hours as 10 x 24 = 240 hours, and the required date as 07-FEB - 3 days = 02-FEB. 05-FEB and 06-FEB are non workdays.

Item Master Schedule Date Master Schedule Qty Required Hours Required Date
A 07-FEB 10 240 02-FEB
A 10-FEB 10 240 07-FEB
A 15-FEB 10 240 10-FEB

The following table illustrates how routing-based RCCP buckets the required hours for D1, R2 into weekly buckets. The example assumes that the first bucket starts on 31-JAN.

Week Start Date Department Resource Required Hours
31-JAN D1 R2 240
07-FEB D1 R2 480

Available Hours Calculation

Routing-based RCCP calculates available hours for a resource using the resource availability information you define in Oracle Bills of Material.

You can define resources, departments, shifts, and shift calendars in Oracle Bills of Material. Having defined your departments, resources, and shifts, you can assign shifts to resources and resources to departments.

Routing-based RCCP calculates available hours for a resource by summing the available hours for each shift that uses the resource using the following formula:


For 24-hour resources, routing-based RCCP modifies the formula as follows:


Capacity units represents the number of resource units available to a department. Shift hours per day and shift days per week reflect the availability times you specify for each shift. Workdays per week reflect the number of workdays in the week based on the workday calendar you define using the Define Workday Calendar window in Oracle Bills of Material.

The following table illustrates how routing-based RCCP would calculate available hours for D1, R2 assuming that you have assigned it to two shifts, Shift 1 and Shift 2. In this example, the available hours for D1, R2 on Shift 1 is 2 x 6 x 5 = 60 hours. Routing-based RCCP would calculate the total hours available for D1, R2 as 60 + 80 = 140 hours per week.

Shift Capacity Units Shift Hours/Day Shift Days/Week Available Hours
Shift 1 2 6 5 60
Shift 2 2 8 5 80

Utilization Calculation

Routing-based RCCP calculates capacity utilization for each resource by dividing the total required hours per week by the total available hours per week, using the following formula:


The following table illustrates how routing-based RCCP would calculate capacity utilization for D1, R2 for the weeks starting 31-JAN and 07-FEB. In this example, the capacity utilization for D1, R2, for the week starting 31-JAN, is 240/140 x 100% = 171%

Week Start Date Required Hours Available Hours Capacity Utilization
31-JAN 240 140 171%
07-FEB 480 140 343%

Notice that rough cut analysis reveals that D1, R2 is overloaded in both periods. This is illustrated in the following diagram.

See Also

Defining a Department

Defining a Resource


         Previous  Next          Contents  Index  Navigation  Glossary  Library