Overview of Resource Requirements Snapshot

The first step in calculating detailed capacity requirements, for both routing and rate-based CRP, is to load resource requirements from Oracle Bills of Material and Oracle Work in Process. This is done by the Snapshot during the planning process.

The capacity requirements calculated for each resource by routing-based CRP represent the summation of the requirements generated by planned orders, suggested repetitive schedules, discrete jobs, and non-standard jobs. The Snapshot loads resource requirements for planned orders and suggested repetitive schedules from Oracle Bills of Material and loads resource requirements for discrete and non-standard jobs from Oracle Work in Process.

The resource requirements loaded from Oracle Bills of Material are also used by rate-based CRP when calculating rate requirements on production lines.