Previous  Next          Contents  Index  Navigation  Glossary  Library

Implementation of ECOs on Jobs and Schedules

You can indicate whether to update work in process requirements when you implement an ECO revised item. When you implement the revised item that is set to update work in process, the bill of material is automatically re-exploded and updated for all unreleased discrete jobs and repetitive schedules for the item.

If you have updated component material requirements for the unreleased job or schedule, you lose these updates after you implement the revised item.

Released, Complete, and On hold Repetitive Schedules

For repetitive schedules, if you have not moved assemblies beyond the Queue intraoperation step of the first operation, Work in Process automatically regenerates the bill and component requirements for the repetitive schedule to include the effects of the ECO.

If you have moved assemblies beyond the Queue intraoperation step of the first operation, when you implement the ECO, Work in Process splits the schedule into two schedules that take the place of the original schedule. The first schedule uses the original bill and the second new schedule uses the revised bill that includes any revised item or component changes. Work in Process assigns the two new schedules a status of Released, Complete, or On hold, depending on the status of the original schedule.

The schedule splits based on the number of assemblies in process (moved past the Queue intraoperation step of the first operation if you are using routings) on the original routing. That number is rounded up to the nearest day so that you can finish your day's work using the original bill. The next day production starts using the revised bill and a new schedule.

The following example best illustrates this procedure.

Example

Released Schedule:

The following diagram illustrates the original schedule:

Shop floor distribution of assemblies before the implementation of the ECO for the original schedule:

Original schedule dates:

Since the daily quantity is 50, this means that production is in its second day. Therefore, if you implement the ECO now, the schedule splits after the second day's work is completed.

If you implement a change order for the item on Day 3 (Today), the shop floor distribution of assemblies following the implementation of the ECO are:

New Schedule 1 = 100 total units

New Schedule 2 = 100 total units

Schedule dates following the implementation of the ECO:

New Schedule 1:

New Schedule 2:

The following diagram illustrates the split schedule:

All material that you issued to the original schedule remains with new schedule 1. Material requirements for new schedule 1 are changed to match the new number of assemblies to complete. Material requirements for the altered assembly are exploded for new schedule 2 for the number of assemblies assigned to the new schedule 2.

See Also

Overview of Discrete Manufacturing

Overview of Repetitive Manufacturing


         Previous  Next          Contents  Index  Navigation  Glossary  Library