Testing What-if Scenarios
You can make changes to either capacity or materials and see the effects of these changes on your plan.
To test the effect of a change in resources or materials, do this:
1. Navigate to the Planner Workbench.
2. Find the plan in which you want to test what-if scenarios.
3. To make changes to capacity available for this plan, navigate to the Available Resources window. Then change the date, capacity units, or daily capacity for any resource.
4. To make changes to material supply or demand, navigate to the Supply, Demand, or Supply/Demand window. Then make any changes you want, such as Quantity, Date, Alternate Routing, Alternative BOM.
6. In the Planner Workbench window, choose either Online or Batch in the Net Change Replan region, then choose Plan.
7. Re-query the plan to review the effects of your changes.
To implement and release your modified plan:
See Also
Overview of Net Change Replan
Identifying Capacity Problems