Defining a Schedule Name

Before you define a master schedule manually or load a schedule from another source, you first define a name. You can also set several options for each name.

Defining an MPS name in Supply Chain Planning involves extra steps. Supply Chain Planning users should refer to Defining a Supply Chain MPS Name for further instructions.

If you launch a plan with an MPS names, you can also make a copy that is identical to the original. You can then view, implement, and replan either copy, discarding the altered plan at any time and preserving the original data. See: Making a Copy of a Completed Plan.

   To define a schedule name:

   To set additional MPS options

   To set relief options for a schedule name:

In addition to the steps above, enter the following information:

   To disable a schedule name:

See Also

Defining Schedule Entries Manually

Schedule Relief

Available to Promise (ATP)