Rescheduling Repetitive Schedules

You can reschedule repetitive schedules with and without routings. When you change a repetitive schedule quantity, the system automatically prompts you to choose the date around which you want to reschedule. The number of processing days increases/decreases to reflect the quantity change.

When you update the number of workdays, you must choose the date around which you want to reschedule. The current schedule is rescheduled around the date you specify.

You can enter first unit/last unit start (FUCD/LUSD) and first unit/last unit completion (FUCD/LUCD) dates and times earlier than the current date and time to maintain relative date priorities for department schedules and material requirements.

Prerequisites

   To reschedule a repetitive schedule with a routing or a fixed lead time repetitive schedule without a routing:

   To reschedule a repetitive schedule without a routing that has a routing-based lead time:

   To reschedule a repetitive schedule after changing the daily quantity, the processing days, or the total quantity:

See Also

Defining Repetitive Schedules Manually

Changing Repetitive Schedules

Repetitive Line Scheduling

Repetitive Line Rescheduling