Reports

This chapter covers the following topics:

Overview of Reports

This section explains how to submit report requests and briefly describes each Capacity report. For additional information on planning reports and processes, see Reports, Oracle Master Scheduling/MRP and Oracle Supply Chain Planning.

Bill of Resources Report

Use the Bill of Resources Report to review your bills of resources. You can use bills of resources to calculate rough cut capacity plans for your master schedules without defining detailed bills or routings. You can also simulate different manufacturing methods as well as long–term plan resource requirements by defining multiple bills of resources for items. You can also use a bill of resource to simulate changes to existing routings and bills of material.

Report Submission

In the Submit Requests window, enter Bill of Resources Report in the Name field.

Report Parameters

Bill of Resource Set: Enter the name of the bill of resource set.

Resource Group: Enter a resource group to restrict the capacity plan to the resources contained within the group.

Items From/To: To restrict the report to a range of items, select the beginning and ending item numbers

See Also:

Submitting a Request, Oracle Applications User's Guide

CRP Rate-Based Report

The CRP Rate–Based Report displays detailed capacity information for repetitively planned items manufactured on rate based lines for a selected material requirements plan. You can display the report information in a combination of weekly and periodic buckets. You can report on lines where load ratio falls below or exceeds a specified percentage. You can report capacity information on all production lines, a range of lines, or a specific line. You can optionally include requirements details that displays each resource requirement along with information pertaining to the source of the requirement.

Note: You can launch this report from Master Scheduling/MRP and Oracle Supply Chain Planning modules.

Report Submission

In the Submit Requests window, enter CRP Rate–Based Report in the Name field.

Report Parameters

See Also:

CRP Routing-Based Report

The CRP Routing-Based Report displays the capacity requirements plan for a given material requirements plan you specify, as well as information on resource availability. You can use this information to adjust capacity and/or the MRP or MPS plans. You can sort the report by department or resource. You can include requirements and cost detail. You can specify the periods and number of weeks within the periods for which to display information. You can display modified capacity information for a selected simulation set. You can report on aggregate requirements for multi–department resources.

Note: You can launch this report from Master Scheduling/MRP and Oracle Supply Chain Planning modules.

Report Submission

In the Submit Requests window, enter CRP Routing-Based Report in the Name field

Report Parameter

See Also

RCCP Rate-Based Report

The RCCP Rate-Based Report displays the rough-cut capacity information for repetitively planned items manufactured on rate based lines for a selected master schedule and a bill of resource. You can display the report information in a combination of weekly and periodic buckets. You can report on lines where load ratio falls below or exceeds a specified percentage. You can report rough-cut capacity information on all lines, a range of lines, or a specific line.

Note: You can launch this report from Master Scheduling/MRP and Oracle Supply Chain Planning modules.

Report Submission:In the Submit Requests window, enter RCCP Rate-Based Report in the Name field.

Report Parameters

See Also:Submitting a Request, Oracle Applications User's Guide

RCCP Routing-Based Report

The RCCP Routing-Based Report displays the rough-cut capacity for a master schedule you specify, as well as information on resource availability. This report shows what resources are required for your future production tasks based on a master schedule. This allows you to adjust capacity and/or the master schedule to ensure that you can produce the master schedule. You can sort the report by department or resource. You can include requirements and cost detail. You can specify the periods and number of weeks within the periods for which to display information. You can report rough–cut capacity plans for a selected bill of resource and you can report on aggregate requirements for multi-department resources. You can display modified capacity information for a selected simulation set.

Note: You can launch this report from Master Scheduling/MRP and Oracle Supply Chain Planning modules.

Report Submission: In the Submit Requests window, enter RCCP Routing-Based Report in the Name field.

Report Parameters:

See Also: