1.  Preparing to Install the Rack

Installing the Rack Task Overview

Observing Safety Guidelines and Warnings

Verifying Requirements

Size and Space Requirements

Access Route Guidelines

Power Requirements

Grounding Requirements

Airflow Requirements

Electrostatic Discharge Prevention

Preparing the Installation Site

Mounting Holes and Cable Routing Floor Cutout

Leveling Feet and Castor Dimensions

Cable Routing Space Dimensions

Sun Rack II 1042 Rear Cabling Space

Sun Rack II 1242 Rear Cabling Space

Top Cable Window Dimensions

2.  Installing the Rack

Unpacking the Rack

Differences Between Standard and Enterprise Packaging

Tools Required

Moving the Rack to the Installation Site

Move the Rack to the Installation Site

Stabilizing the Rack

Stabilize the Rack With the Mounting Brackets

Stabilize the Rack With the Leveling Feet

Attaching an Optional Ground Cable

Attach a Ground Cable

3.  Installing Equipment Into the Rack

Installing Equipment Task Overview

Observing Equipment Installation Guidelines

Preparing to Install Equipment Into the Rack

Using the Anti-Tilt Legs

Taking Antistatic Precautions

Adjusting the RETMA Rails

Preparing Factory-Installed Power Distribution Units

Installing Power Distribution Units

Insert Cage Nuts Into Rail Holes

Using the Cable Management Hooks

Installing Equipment Into the Rack

Installing Optional Components

Install Filler Panels

Install Third-Party Cable Trays

4.  Servicing the Rack

Servicing Equipment in the Rack

Observing Equipment Service Guidelines

Servicing Power Distribution Units

Powering the Rack Off and On

Power the Rack Off

Power the Rack On

Locating and Disconnecting Panel Grounding Straps

Disconnect a Grounding Strap

Removing and Replacing the Doors

Remove the Doors

Replace the Doors

Removing and Replacing the Side Panels

Remove the Side Panels

Replace the Side Panels

Removing and Replacing Filler Panels

Remove Filler Panels

Replace Filler Panels

Removing and Replacing the Top Panel

Remove the Top Panel

Replace the Top Panel

5.  Repacking a Rack for Shipment

Securing the PDUs in the Rack

Secure the PDUs in the Rack

Repacking the Rack in the Enterprise Packaging

Repack the Rack in the Enterprise Packaging

Index

A

C

D

E

F

G

I

K

L

M

P

R

S

T

U

W

C

cable
management hooks, index iconUsing the Cable Management Hooks
spring nuts, installing, index iconInstall a Cable Management Hook
routing
brackets, PDU, index iconPrepare Factory-Installed PDUs
space dimensions, index iconCable Routing Space Dimensions
trays, mounting holes, index iconInstall Third-Party Cable Trays
cabling
floor cutout
1042 dimensions, index iconMounting Holes and Cable Routing Floor Cutout
1240 dimensions, index iconMounting Holes and Cable Routing Floor Cutout
preparing, index iconMounting Holes and Cable Routing Floor Cutout
grounding cable, index iconAttaching an Optional Ground Cable
management hooks, index iconUsing the Cable Management Hooks
PDU input lead cords, index iconPrepare Factory-Installed PDUs
cage nut
Duosert, installing, index iconInstall Filler Panels
filler panel, index iconInstall Filler Panels
insertion tool, index iconInsert Cage Nuts Into Rail Holes
installing, index iconInsert Cage Nuts Into Rail Holes
castor dimensions, index iconLeveling Feet and Castor Dimensions
circuit breakers, index iconPower the Rack Off
compliance guidelines, index iconObserving Safety Guidelines and Warnings