3 Site Preparation
This chapter describes the tasks you must complete before installing
Oracle Database Appliance. It includes:
System Installation Task Checklist
The following table lists the tasks you must perform to properly install
the system. These tasks must be performed in the order they appear in the
table.
| | |
1
| Access the online product documentation.
| |
2
| Review safety information.
| Before performing the installation, see the following documents:
|
3
| Review system features and components.
| |
4
| Complete the site preparation procedures.
| |
5
| Rackmount the system.
| |
6
| Connect cables.
| |
7
| Connect to Oracle ILOM.
| |
8
| Power.
| |
|
Prepare Your Site
Use the following procedure to prepare your site for Oracle Database
Appliance installation:
To Prepare Your Site
- Ensure that your site meets the environmental requirements in Environmental Specifications.
- Ensure that your site meets the electrical specifications in Electrical Specifications.
- Ensure that your site has adequate clearance for the shipping
containers.
The shipping box measures 91.12 x 60.66 x 53.50 cm
(35.87 x 23.88 x 21.06 inches).
- Open the shipping container.
You should do this at
the location where the system will be installed.
- Check the contents of the shipping container.
It should
contain:
See Also
Chapter 4, Installing the System into
a Rack
Environmental and Electrical Requirements
This section includes:
Environmental Specifications
The following table lists the environmental requirements for a single,
non-racked Oracle Database Appliance installation.
| |
Operating temperature
| 5° C to 35° C
(41° F to 95° F).
|
Nonoperating temperature
| -40° C to 70° C
(-40° F to 158° F).
|
Operating humidity
| 10% to 90% relative humidity, noncondensing.
|
Nonoperating humidity
| Up to 93% relative humidity, noncondensing.
|
Operating altitude
| Up to 9,840 feet (3000 m*). Maximum ambient temperature is derated by
1 oC per 300 m (984 ft) above 900 m (2,953 ft), * Except in China markets where regulations might limit installations
to a maximum altitude of 2000 m (6562 ft).
|
Nonoperating altitude
| Up to 12,000 m (39,370 ft).
|
Airflow
| 130 CFM typical; 250 CFM maximum.
|
|
Electrical Specifications
The following table lists the input electrical
specifications for Oracle Database Appliance.
| |
Nominal frequencies
| 50-60 Hz
|
Nominal voltage range
| 100 VAC 110-127 VAC 200-240 VAC
|
Maximum current AC RMS
| 12A maximum at 110-127 VAC 7A maximum at 200-240 VAC 13A maximum at 100 VAC (Japan only)
|
AC operating range
| 90-264 VAC
|
Maximum power consumption
| 1270W at 100-120 VAC 1370W at 200-240 VAC
|
Volt-Ampere (VA) rating
| 1400 VA at 240 VAC, 0.98 P.F.
|
|
The following table lists the output electrical
specifications for Oracle Database Appliance.
| |
3.3 VDC STBY
| 4.0A
|
+12 VDC
| 90.8A at 100-127 VAC 99.2A at 200-240 VAC
|
|