Burn-In Testing

Burn-in testing enables you to run test scripts and to create new scripts.

The main menu provides two burn-in selections, Immediate Burn-In Testing and Deferred Burn-In Testing.

  • Immediate Burn-In Testing allows you to run a test script, which you can modify, or run as is.

  • Deferred Burn-In Testing allows you to modify existing test scripts or create new ones. To actually run the new or modified scripts, you must use Immediate Burn-In Testing.