Oracle Project Management Flows

Overview

Oracle Project Management provides project managers the visibility and control to deliver projects successfully, improve profitability, and operate more efficiently. Oracle Project Management empowers project managers to plan work, assign resources, forecast to completion, and communicate to stakeholders, while streamlining the collaborative execution of project work.

The following sections describe the flows in Oracle Project Management advanced pack.

Project Management Setup Flow

This flow covers the creation of following setups:

Attributes

This section provides information on prerequisites, profile options, and data setups required to execute the Project Management Setup flow.

Technical Name

PJT__Project_Setups

Prerequisites

The following are the prerequisites for executing this flow:

Profile Options

Not applicable.

Predefined Data

The following predefined data must be used:

Window Name Field Name Field Value
User User Name services
  Password welcome
Responsibilities Responsibility Name Projects SU, Vision Services (USA)
Projects, Vision Services (USA)
General Ledger, Vision Services (USA)
Human Resources, Vision Enterprises
Receivables, Vision Services (USA)

Setup Data

The following data must be set up:

Page Name Field Name Field Value Comments
Planning Resource List Job Group Vision Corporation Job flexfield and Business Group is Vision Corporation.
Planning Resource List Employee Name Marlin, Ms. Amy Employee exists in Human Resources with active assignment.
Planning Resource List Employee Name Heather, Ms. Emily Employee exists in Human Resources with active assignment.
Planning Resource List Non Labor Resource-Organization Crane - Services-East Crane is a nonlabor resource with the following setup details:
  • Expenditure type - Shop floor

  • Equipment resource class - selected

  • Services-East Organization assigned


Services-East organization is created with the following setup details
  • Organization Type - Department

  • Classifications - Project Expenditure or Event

  • Organization - Project Task Owning Organization

Planning Resource List Item - Organization CM23987 - Vision Svcs 1
  • ItemCM23987 is available with Item Cost as 500 for the cost type AvgRates, and organization assignment is Vision Svcs 1 organization

  • UOM as @Each

  • Vision Svcs 1 organization with Organization Type for the organization as Department, and the classifications as Inventory Organization, MRP Organization, Project Expenditure/Event Organization, Project Task Owning Organization, Project Manufacturing Organization, or WIP Organization.

Planning Resource List Expenditure Type Airfare
  • Expenditure Type as Air Fare

  • UOM - Currency

  • Rate Required - No

  • Expenditure Type Class - Expense Reports, Supplier Invoices

Planning Resource List Financial Elements Financial Elements
  • Spread Curve - Even

  • Forecast ETC Method - Remaining Plan

Control Item Type Status List BF Status List Create a status list named BF with these statuses:
System Status  
Draf Draft
Submitted BF-Submitted
Approved BF-Approved

BF-Submitted user status should have 'Allow rework on control items' and 'Allow control item' actions selected.
BF Approved user status should have 'Allow control item impact implementation' and 'Allow cancellation of control items' selected.
Billing Accounts Customer Name Hilman and Associates Customer should be created in Accounts Receivables module with address as: 1200 West 129th Street TULSA, OK 74126, with Bill To and Ship To purpose
Billing Accounts Contact Lewis, Betty Contact for the customer Hilman and Associates with a job title should be created.
Create Tasks Task Type DSN-PE-Effort DSN-PE-Effort task type should have these values:
  • Progress Entry Required - Yes

  • Initial progress Status - On Track

  • Physical Percent Complete derivation method - Effort

  • Enable Measurement Collection - No

  • Enable Actual and ETC collection - Yes

    DSN-PE-Cost DSN-PE-Cost task type should have these values:
  • Progress Entry Required - Yes

  • Initial progress Status - On Track

  • Physical Percent Complete derivation method - Cost

  • Enable Measurement Collection - No

  • Enable Actual and ETC collection - Yes

    DSN-PE-Deliverable DSN-PE-Deliverable task type should have these values:
  • Progress Entry Required - Yes

  • Initial progress Status - On Track

  • Physical Percent Complete derivation method - Deliverables

  • Enable Measurement Collection - No

  • Enable Actual and ETC collection - Yes

    DSN-PE-WQ DSN-PE-WQ task type should have these values:
  • Progress Entry Required - Yes

  • Initial progress Status - On Track

  • Enable Work Quantity - Yes

  • Work Item - Test Plan

  • Unit of Measure - Cases

  • Actual Work Quantity Entry Method - Actual Work Quantity to Date

  • Enable Measurement Collection - Yes

  • Physical Percent Complete derivation method - Work Quantity

  • Enable Actual and ETC collection - Yes

Budgeting and Forecasting Plan Type Approved Budget Approved Budget plan type should have these values:
Setup Options:
  • Approve Cost Budget - Yes

  • Approved Revenue Budget - Yes

  • Allow Edit after Initial Baseline - Yes


Conversion Attributes:
Project Functional Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period


Project Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period

Budgeting and Forecasting Plan Type Primary Forecast Primary Forecast Plan type should have these values:
Setup Options:
  • Primary Cost Forecast - Yes

  • Primary Revenue Forecast - Yes


Conversion Attributes:
Project Functional Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period


Project Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period

Budgeting and Forecasting Plan Type Cost Rate Type- DHI Corporate Conversion Rate Type - DHI Corporate should be available.
Daily Rates for different currencies should be maintained.
Window Name Field Name Field Value Comments
Rate Schedule Oraganization Vision Services Organization type for the organization should be Division, and the classifications Operating Unit and Project Task Owning Organization should be attached.
Rate Schedule Job CON600.Consultant Active job should be created under Vision Corporation job group.
Rate Schedule Expenditure Type Shopfloor Expenditure type Shopfloor with Expenditure category - Labor
Revenue category - Labor
UOM - Hours
Rate Required - No
Expenditure Type Class - Straight Time and Usages
Project Type Service Type Administration Service Type Lookup should have a record with code Administration.
Project Type Work Type Commercial Customer-billable Work Type Commercial Customer-billable with Billable or Capitalizable - Yes
Transfer Price Amount Type - Cost Transfer
Project Type Resource List Expenditure Category Expenditure Category resource list with:
  • Job Group - Vision Corporation

  • Group Resource by - None

  • Resource Type - Expenditure category

  • Resource - Labor

Team Member Role Project Manager Project Manager Role should be created
All Available controls should be assigned

Workplan Planning to Project Execution Fully Shared Flow

This flow covers the creation of a project from a template created in Project Management Setup flow. This flow includes the following:

Attributes

This section provides information on prerequisites, profile options, and data setups required to execute the Workplan Planning to Project Execution Fully Shared flow.

Technical Name

PJT_Workplan_Plan_To_Execution_FSVE

Prerequisites

The following are the prerequisites for executing this flow:

Profile Options

Not applicable.

Predefined Data

The following predefined data must be used:

Window Name Field Name Field Value
User User Name services
  Password welcome
Responsibilities Responsibility Name Projects SU, Vision Services (USA)
Projects, Vision Services (USA)

Setup Data

The following data must be set up:

Page Name Field Name Field Value Comments
Pre-Approved Batch Expenditure Type Professional Expenditure category - Labor
Revenue category - Labor
UOM - Hours
Rate Required - No
Expenditure Type Class - Straight Time
Pre-Approved Batch Expenditure Type Airfare Expenditure category - Other Expenses
Revenue category - Direct
UOM - Currency
Rate Required - No
Expenditure Type Class - Miscellaneous Transaction

Deliverables Billing and Procurement Action Fully Shared Flow

This flow covers the creation of a project from a template created in the Project Management Setup flow. This flow includes the following:

Attributes

This section provides information on prerequisites, profile options, and data setups required to execute the Deliverables Billing and Procurement Action Fully Shared flow.

Technical Name

PJT_Deliverable_Action_Exe_Prog_FSVE

Prerequisites

The following is a prerequisite for executing this flow:

Profile Options

Not applicable.

Predefined Data

The following predefined data must be used:

Window Name Field Name Field Value
User User Name services
  Password welcome
Responsibilities Responsibility Name Projects SU, Vision Services (USA)
Projects, Vision Services (USA)
Manufacturing and Distribution Manager, Vision Services (USA)
Purchasing, Vision Services (USA)

Setup Data

The following data must be set up:

Page Name Field Name Field Value Comments
Deliverable Action Receiving Location Costa Mesa, CA Location should be created in Oracle Manufacturing as follows:
  • Scope - Global

  • Shipping Details tab-Ship to Location - Costa Mesa, CA

  • Ship to Site - Yes

  • Receiving Site - Yes

  • Office Site - Yes

  • Bill to Site - Yes

  • Internal Site - Yes

  • Inventory Organization- VS1-Vision Svcs 1

    Adelaide
  • Scope - Global

  • Shipping Details tab-Ship to Location - Costa Mesa, CA

  • Ship to Site - Yes

  • Receiving Site - Yes

  • Office Site - Yes

  • Bill to Site - Yes

  • Internal Site - Yes

Window Name Field Name Field Value Comments
Auto Create Documents (Find Requisition Lines) Supplier Allied Manufacturing Supplier Allied Manufacturing with site as TORRANCE
Receipt Subinventory Stores  

Change Management to Financial Plan Implementation Fully Shared Flow

This flow includes the following:

Attributes

This section provides information on prerequisites, profile options, and data setups required to execute the Change Management to Financial Plan Implementation Fully Shared flow.

Technical Name

PJT_ChangeReq_Order_Imp_FSVE

Prerequisites

The following is a prerequisite for executing this flow:

Profile Options

Not applicable.

Predefined Data

The following predefined data must be used:

Window Name Field Name Field Value
User User Name services
  Password welcome
Responsibilities Responsibility Name Projects SU, Vision Services (USA)
Projects, Vision Services (USA)
Receivables, Vision Services (USA)

Setup Data

The following data must be set up:

Page Name Field Name Field Value Comments
Change Order Control Item Type BF-Change Order BF-Change Order control item type should be present with the following data:
  • Status of the list - BF Status List

  • Selected Impacts as Workplan, Supplier, Staffing, Other, Financial

  • Budget Update Method - Edit Budget lines

  • Revenue - Yes

  • Cost - Yes

  • This control item type should be assigned to Financial Plan Type - Approved Budget

Window Name Field Name Field Value
Agreement Terms 30 Net

Budgeting and Forecasting Fully Shared Flow

This flow covers the following:

Attributes

This section provides information on prerequisites, profile options, and data setups required to execute the Budgeting and Forecasting Fully Shared flow.

Technical Name

PJT_Budget_And_Forecast_Generation_FSVE

Prerequisites

The following are the prerequisites for executing this flow:

Profile Options

Not applicable.

Predefined Data

The following predefined data must be used:

Window Name Field Name Field Value
User User Name services
  Password welcome
Responsibilities Responsibility Name Projects SU, Vision Services (USA)
Projects, Vision Services (USA)

Setup Data

The following data must be set up:

Page Name Field Name Field Value Comments
Pre-approved batch Expenditure Type Professional
  • Expenditure category - Labor

  • Revenue category - Labor

  • UOM - Hours

  • Rate Required - No

  • Expenditure Type Class - Straight Time

Workplan Planning to Progress Partially Shared Flow

This flow includes the following:

Attributes

This section provides information on prerequisites, profile options, and data setups required to execute the Workplan Planning to Progress Partially Shared flow.

Technical Name

PJT_Plan_To_Progress_PSVE

Prerequisites

The following is a prerequisite for executing this flow:

Profile Options

Not applicable.

Predefined Data

The following predefined data must be used:

Window Name Field Name Field Value
User User Name services or eheather
  Password welcome
Responsibilities Responsibility Name Projects SU, Vision Services (USA)
Team Member, Vision Services (USA)

Setup Data

The following data must be set up:

Page Name Field Name Field Value Comments
Task Details Unit of Measure Square Feet Projects Lookups - UNIT
Code - SF
Meaning - Square Feet
Description: Square Feet
Tag - N
Effective Dates From - 01-JAN-2005
Enabled - Yes
Task Details Work Item Concrete Finishing Projects Lookups - PA_WQ_WORK_ITEMS
Code - CONC FINISH
Meaning - Concrete Finishing
Description - Concrete Finishing
Tag - N
Effective Dates From - 01-JAN-2003
Enabled - Yes

Program Management Between Split Mapped and Fully Shared Flow

This flow is related to progress rollup from project to program, and program to program. The following are created in the flow:

  1. Employee Rate Schedule

  2. Job Rate Schedule

  3. Nonlabor Rate Schedule

  4. Labor Costing Override

  5. Burden Structure

  6. Burden Schedule

  7. Planning Resource List

  8. Resource Breakdown Structure

  9. Project Template

  10. Program Template

  11. Project and Program creation

This flow associates a Fully Shared Version Enabled (FSVE) project to a FSVE program and then FSVE program to Non-Shared: No Mapping Version Enabled (SPVE) program as a link project. Actual entry, budget creation, and forecast generation is linked at project and program levels. The flow verifies progress rollup to program from linked project. This flow also verifies performance overview at Project and Program level for resource and task summary.

Attributes

This section provides information on prerequisites, profile options, and data setups required to execute the Program Management Between Split Mapped and Fully Shared flow.

Technical Name

PJT_Program_Management_Setups

PJT_Program_Plan_To_Actual_To_Reporting

Prerequisites

The following are the prerequisites for executing this flow:

Resource Class Rate
People 10
Equipment 20
Material Items 1
Financial Element 1
Resource Class Rate Markup Percent
People 30 0
Equipment 60 0
Material Items 0 30
Financial Element 0 10

Profile Options

Not applicable.

Predefined Data

The following predefined data must be used:

Window Name Field Name Field Value
User User Name services
  Password welcome
Responsibilities Responsibility Name Projects SU, Vision Services (USA)
Projects, Vision Services (USA)

Setup Data

The following data must be set up:

Page Name Field Name Field Value Comments
Planning Resource List Job Group Vision Corporation Job flexfield and Business Group is Vision Corporation.
Planning Resource List Job Name CON600.Consultant Active Job to be created under Vision Corporation job group
Team Member Employee Name Marlin, Ms. Amy Employee exists in Human Resources with active assignment.
Planning Resource List Employee Name Heather, Ms. Emily Employee exists in Human Resources with active assignment.
Financial Plan Non Labor Resource - Organization Crane - Services-East Crane is a nonlabor resource with the following setup details:
  • Expenditure type - Shop floor

  • Equipment resource class - selected

  • Services-East Organization assigned

Financial Plan Non Labor Resource - Organization Personal Personal is a nonlabor resource with the following setup details:
  • Expenditure type - Computers

  • Equipment resource class - selected

  • Services-East Organization assigned

Financial Plan Expenditure Type Shop floor
  • Expenditure Type as Shop floor

  • UOM - Hours

  • Rate Required - Yes

  • Expenditure Type Class - Usages

Project Template Organization or Operating Unit Vision Services Organization type for the organization should be Division and the classifications Operating Unit and Project Task Owning Organization should be attached.
Project Template Project Type Cost Plus
  • Project Type Cost Plus has Type class as Contract Burdened Enabled

  • Resource List is Expenditure Category

  • Funding Level is Both

  • Billing Job Group is Vision Corporation

  • Labor Invoice formats is Employee

  • Nonlabor invoice formats is Expenditure Type

  • Default Distribution rule is Work/Work

Team Member Role Project Manager
  • Project Manager Role should be created

  • All Available controls should be assigned

Billing Accounts Customer Hilman and Associates Customer should be created in Oracle Accounts Receivables module with address as: 1200 West 129th Street TULSA, OK 74126
Add Bill To and Ship To purpose
Billing Accounts Customer Name Hilman and Associates Customer should be created in Accounts Receivables module with address as: 1200 West 129th Street TULSA, OK 74126, with Bill To and Ship To purpose
Billing Accounts Contact Name Gasper, Danielle Gasper, Danielle should be added as a contact detail to Customer Hilman and Associates.
Classification Class Category Product  
Classification Class Code Product1  
Work Breakdown Structure Task Type DSN-PE-Effort DSN-PE-Effort task type should have these values:
  • Progress Entry Required - Yes

  • Initial progress Status - On Track

  • Physical Percent Complete derivation method - Effort

  • Enable Measurement Collection - No

  • Enable Actual and ETC collection - Yes

    DSN-PE-Cost DSN-PE-Cost task type should have these values:
  • Progress Entry Required - Yes

  • Initial progress Status - On Track

  • Physical Percent Complete derivation method - Cost

  • Enable Measurement Collection - No

  • Enable Actual and ETC collection - Yes

    DSN-PE-WQ DSN-PE-WQ task type should have these values:
  • Progress Entry Required - Yes

  • Initial progress Status - On Track

  • Enable Work Quantity - Yes

  • Work Item - Test Plan

  • Unit of Measure - Cases

  • Actual Work Quantity Entry Method - Actual Work Quantity to Date

  • Enable Measurement Collection - Yes

  • Physical Percent Complete derivation method - Work Quantity

  • Enable Actual and ETC collection - Yes

Work Breakdown Structure Work Type Test plan  
Work Plan Setting Cost Rate Type Name DHI-Corporate Conversion Rate Type - DHI Corporate should be available
Daily Rates for different currencies should be maintained
Financial Plan Plan Type Approved Budget Approved Budget plan type should have these values:
Setup Options:
  • Approve Cost Budget - Yes

  • Approved Revenue Budget - Yes

  • Allow Edit after Initial Baseline - Yes


Conversion Attributes:
Project Functional Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period


Project Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period

Financial Plan Plan Type Primary Forecast Primary Forecast Plan type should have these values:
Setup Options:
  • Primary Cost Forecast - Yes

  • Primary Revenue Forecast - Yes


Conversion Attributes:
Project Functional Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period


Project Currency:
  • Cost Rate Type - DHI Corporate

  • Cost Rate Date Type - Start date of plan period

  • Revenue Rate Type - DHI Corporate

  • Revenue Rate Date Type - Start date of plan period

Window Name Field Name Field Value Comments
Burden Structure Expenditure Type Computers, Hotel, Meals, Outside Processing, Other Trades, Professional, Shopfloor  
Burden Structure Burden Cost Base Expense, Labor, Material Cost base has base type as Burden
Burden Structure Burden Cost Code G & A Fee, Material Overhead
  • Cost Code G & A

  • Expenditure Type G & A

  • Cost Code Fee with exp type Fee

  • Material with exp type Material

  • Overhead with exp type Overhead

Burden Structure Burden Cost Base Expense, Labor, Material Cost base has base type as Burden
Rate Schedule Expenditure Type Airfare
  • Expenditure type Air Fare

  • UOM - Currency

  • Rate Required - No

  • Exp Type class - Supplier Invoice

Rate Schedule Organization or Operating Unit Vision Services Organization type - Division
Classifications to be attached are Operating Unit and Project Task Owning Organization
Pre Approved Batch Organization Service East Services-East organization should be created with:
  • Organization type - Department

  • Classifications to be attached are Project Expenditure, Event Organization, or Project Task Owning Organization

Pre Approved Batch Expenditure Type Professional
  • Professional expenditure type - Expenditure

  • Revenue category - Labor

  • UOM - Hours

  • Expenditure type class - Straight Time

    Shop floor
  • Shop floor expenditure type - Expenditure

  • Revenue category - Labor

  • UOM - Hours

  • Expenditure type class - Straight Time and Usages

    Computers
  • Computers expenditure type - Expenditure category - Chargebacks

  • Revenue category - Other

  • UOM - Hours

  • Expenditure type class - Usages

  • Rate enabled with Vision Services Operating unit and Rate - 30

Agreement Term 30 Net