After completing this topic, you will be able to overwrite a checked in document.
Steps:
The Inserting the Date topic is checked in to the server. Open the topic.
Double-click the Inserting the Date topic.
Step 1The topic opens as read-only.
Step 2Select the Explanation frame.
Click the X frame icon.
Step 3Delete the Explanation frame.
Click the Delete menu.
Step 4Click the Frame command.
Step 5Click the Yes button to confirm the deletion.
Step 6The Explanation frame is removed from the frame structure. Save the topic.
Click the File menu.
Step 7Click the Save command.
Step 8Because the document is still checked in to the server, you are prompted to select one of the following:
- Yes to check it out and save it.
- No to save it as a new document.
- Cancel to cancel the save and return to the document.
Step 9Click the Yes button to check out and save the document.
Step 10Notice the green checkmark in the tab indicating that the document has been checked out to you.
Step 11Close the topic.
Click the tab Close button.
Step 12Check in the Inserting the Date topic.
Click the Check in button.
Step 14Enter the desired information into the Comment field. Enter "Removed explanation frame".
Step 15Click the OK button.
Step 16Notice the new version number "2" for the document in the Version column.
Step 17After completing this topic, you are able to overwrite a checked in document.