Bill of Resources Example

The following examples illustrate how the bill of resources load process calculates single level resource requirements for two components, B and C, and rolls them up to their parent item, A, as cumulative resource requirements. The following table illustrates the bill of material for A.

Level Item Quantity
1 A 1
. 2 . B 2
. 2 . C 3

The following table illustrates the corresponding routings and associated resource usages for items A, B, and C.

Item Op Seq Department Resource Basis UOM Usage Rate
A 10 D3 R1 Item HR 4
A 20 D3 R2 Item HR 4
B 10 D2 R1 Item HR 6
B 20 D2 R2 Item HR 6
C 10 D1 R1 Lot HR 8
C 20 D1 R2 Item HR 8