Resource Requirements from Oracle Work in Process

The following table illustrates the resource requirements loaded by the Snapshot from Oracle Work in Process. These are used by routing-based CRP to calculate resource requirements for discrete and non-standard jobs. The example assumes that you have defined a discrete job for 6 units of A, due to complete on 07-FEB. 05-FEB and 06-FEB are non workdays.

Item Op Seq Dept Res Operation Hours Required Operation Hours Expended Operation Start Date
A 10 D3 R1 24 0 03-FEB
A 20 D3 R2 24 0 04-FEB