Project Manufacturing Costing Transactions

When you use Oracle Project Manufacturing, you are able to have organizations which concurrently manufacture for projects and non-project customer orders. However for proper management control purposes, item costs and charges for non-project orders are maintained and tracked distinctly separate from projects.

Cost Groups

Using Project Manufacturing, you can have many projects active at any one time. You can also have items in common (non-project) subinventory. Using cost groups, an item may have a different cost in different projects as well as a unique cost in common inventory, all within the same organization. Item costs can apply to a single project if each project belongs to a distinct cost group, or apply to a group of projects if all projects in the group are assigned to the same cost group. Items in common inventory belong to a system defined cost group and are normally costed distinctly separate from items in projects.

Project Notification

Oracle Project is notified when material transactions cross a project boundary (i.e. from project to non-project, from non-project to project, and between two different projects) or cross the task boundary of the same project. For transactions within the same project, if no specific task is entered, it is assumed to be a transaction within the same task, and hence notification to Projects is not required.

Upon notification, Projects either:

The following table summarizes some important transactions, whether they do and do not notify Oracle Projects, their respective debits and credits, and the cost used in the transaction:

Unless otherwise stated, the cost specified for the debit side of the transaction applies also to the credit side.

Note: MOH stands for material overhead. For information on material overhead charges, see Material Overhead Application.

Note: For Interorganization Transfers, the accounting entries for the Receiving Organization are shaded for clarity.

Purchasing, Inventory, or Order Entry Project Referenced Transaction   Transaction Information   Notify Projects
Account and Cost Debit Credit
Purchase Order Receipt to Receiving Inspection
    Receiving Inspection @ PO Cost XX     No
      Inventory A/P Accrual   XX
Delivery From Receiving Inspection To Inventory
       
 
  Cost Group Material @ PO Cost XX     Yes
      Receiving Inspection   XX
Purchase Order Receipt To Inventory
 
 
 
 
  Receiving Inspection @ PO Cost XX     Yes
      Inventory A/P Accrual   XX
Cost Group Material @ PO Cost XX  
      Receiving Inspection   XX
Sales Order Shipments
    Cost of Goods Sold @ Current Average Cost (in Cost Group) XX     No
      Cost Group Valuation   XX
RMA Receipt
      Into Expense Subinventory   No Entries       N/A
      Into Project Asset Locator   Cost Group Valuation @ Current Average Cost XX     No
      Cost of Goods Sold   XX
RMA Returns
      From Project Locator   Cost Group Valuation @ Current Average Cost (in Cost Group) XX     No
      Cost Group Valuation   XX
Miscellaneous Transactions
      Receipt into Project Locator   Cost Group Valuation @ Current Average (in Project Cost Group) or User-specified Cost XX     Yes
      User-specified account   XX
      Issue from Project Locator   User Specified account @ Current Average (in Project Cost Group) or User-specified Cost XX     Yes
      Cost Group Valuation   XX
Interorganization Transfer
      Direct Transfer: Expense to Expense   No entries        
      Direct Transfer: Standard Org. to Project excluding Expense to Expense   Cost Group Material @ Standard (in Sending Org.) + Freight and Transfer Charges XX     Yes
      Interorg. Payable   XX
Interorg. Receivable @ Standard + Freight and Transfer Charges XX  
      Subinventory Valuation   XX
      Freight Credit   XX
      Transfer Credit   XX
      Direct Transfer: Average to Project, or vice versa, excluding Expense to Expense   Cost Group Material @ Current Average Cost (in Sending Org.) XX     Yes
      Interorg. Payable   XX
Interorg. Receivable @ Current Average Cost (in Sending Org.) + Freight and Transfer Charges XX  
      Organization Valuation   XX
      Freight Credit   XX
      Transfer Credit   XX
      Direct Transfer: Project to Standard excluding Expense to Expense   Subinventory Valuation @ Standard XX     Yes
      Purchase Price Variance (in Receiving Organization) @ Difference Between Cost in Sending and Receiving Org. XX XX
      Interorg. Payable @ Current Average Cost (in Sending Org. Cost Group)   XX
Interorg. Receivable @ Current Average Cost in Cost Group in Sending Org. XX  
      Cost Group Valuation (Sender)   XX
      Interorg Transfer via Intransit: Receipt from Intransit (Standard Org.) into Project Org (FOB Receipt)   Cost Group Material (in Receiving Org.)@ Standard Cost (in Receiving Org.) XX     Yes
      Interorg. Payable   XX
Interorg. Receivable @ Standard Cost XX  
      Intransit Inventory   XX
      Interorg Transfer via Intransit: Receipt from Intransit (Project Org) into Project Org. (FOB Receipt)   Cost Group Material (in Receiving Org.) @ Current Average Cost (in Sending Org Cost Group) XX     Yes
      Interorg. Payable   XX
Interorg. Receivable @ Current Average Cost (in Sending Org. Cost Group) XX  
      Intransit Inventory   XX
      Interorg Transfer via Intransit: Receipt from Intransit (Project Org) into Project Org. (FOB Shipment)   Cost Group Material @ Current Average Cost (in Common Cost Group in Receiving Org.) XX     Yes
      Intransit Payable   XX
      Interorg Transfer via Intransit: Receipt from Intransit into Project Org. (FOB Receipt)   Cost Group Valuation or Expense @ Current Average Cost (in Sending Org.) XX     Yes
      Intransit Inventory   XX
      Interorg Transfer via Intransit: Shipment to Intransit (Project Org.) from Standard Org (FOB Shipment)   Intransit Material @ Standard Cost (in Sending Org.) XX     Yes
      Interorg. Payables   XX
Interorg. Receivable XX  
      Subinventory Valuation   XX
      Interorg Transfer via Intransit: Shipment to Intransit (Project Org.) from Project Org (FOB Shipment)   Intransit Inventory @ Current Average Cost (in Project Cost Group in Sending Org.) XX     Yes
      Interorg. Payables   XX
Interorg. Receivable XX  
      Cost Group Valuation   XX
Subinventory Transfer
      Expense to Expense Subinventory, from or to same or different Project   No entries       N/A
      Different Project or Task, Asset to Asset Locator   Cost Group Valuation (in Receiving Project) @ Current Average Cost (in Cost Group in Sending Project) XX     Yes
      Cost Group Valuation or Expense (in Sending Project)   XX
      Different Project or Task, Asset to Expense Subinventory or vice versa   Cost Group Valuation or Expense (in Receiving Project) @ Current Average Cost in Cost Group (in Sending Project) XX     Yes
      Cost Group Valuation (in Sending Project)   XX
      Project to Non-project, Asset to Asset Subinventory   Organization Valuation @ Current Average Cost (in Project Cost Group) XX     Yes
      Cost Group Valuation (in Sending Project)   XX
      Non-project to Project, Asset to Asset Locator   Cost Group Valuation (in Sending Project) @ Current Average Cost in Common Cost Group XX     Yes
      Organization Valuation   XX
Cycle Count and Physical Inventory
      Count < On hand   Inventory Adjustment @ Current Average Cost (in Cost Group) XX     Yes
      Cost Group Valuation   XX
      Count > On hand   Cost Group Valuation @ Current Average Cost (in Cost Group) XX     Yes
      Inventory Adjustment   XX
Average Cost Update
    Cost Group Valuation @ User-defined Cost Increase/Decrease XX     Yes
      Inventory Adjustment   XX

Project Referenced Manufacturing Transaction   Transaction Information   Notify Projects
Account and Cost Debit Credit
Component Issue and Return Transactions
      Issue Project Expense Job from Project Expense Locator   No Entries XX     No
      Issue (other than Expense to Expense) to Project Job from Project Locator, same Project or Task   WIP Inventory @ Current Average Cost (in Project Cost Group) XX     No
      Cost Group Valuation or Expense   XX
      Issue (other than Expense to Expense) to Project Job from Project Locator, same Project different Task   WIP Inventory @ Current Average Cost (in Project Cost Group) XX     Yes
      Cost Group Valuation or Expense   XX
      Issue (other than Expense to Expense) to Project Job from Common Subinventory   Cost Group Valuation @ Current Average (in Common Cost Group) XX     Yes
      Organization Valuation   XX
WIP Inventory @ Current Average (in Project Cost Group) XX  
      Cost Group Valuation   XX
Resource Charges
      Charge Labor Resource to Project Job   WIP Resource @ Actual Employee Rate or User-defined Cost XX     Yes
      Resource Absorption   XX
      Charge Non-labor Resource to Job   WIP Resource @ User-defined Cost XX     Yes
      Resource Absorption   XX
Overhead Charges
    WIP Overhead Valuation @ User-defined Cost or Rate XX     Yes
      Overhead Absorption   XX
Outside Processing Charges
    WIP Outside Processing @ Purchase Order Cost XX     Yes
      Outside Processing Absorption   XX
Assembly Scrap Transactions
 
      Scrap
  Scrap @ Calculated Scrap value XX     No
      WIP Accounting Class Valuation   XX
      Reverse Scrap   WIP Accounting Class Valuation XX     No
      Scrap @ Calculated Scrap value   XX
Assembly Completion Transactions
      Complete Assemblies from Project Job into Asset Project Locator   Cost Group Valuation @ User-defined or System Calculated + MOH XX     Yes (for MOH amount only)
      WIP Accounting Class Valuation   XX
      Material Overhead Absorption   XX
Job Close Transactions
    WIP Accounting class variance XX     No
      WIP accounting class valuation   XX