CRP Reports
You can launch the following reports from Master Scheduling/MRP and Oracle Supply Chain Planning modules:
- RCCP Routing Based Report
The CRP Rate Based Report shows a breakdown of required rate coming from four possible sources: planned orders, non-standard jobs, discrete jobs, and repetitive schedules. The RCCP Rate Based Report does not contain this detail information.
Since RCCP by nature is just an estimate of resources required, a detailed breakdown of required rate is not included in the report.