Master Schedule Load

Forecasts

You can specify the following demand time fence options when you load forecasts into a master schedule.

Load Sales Orders within and Forecast Outside Demand Time Fence

Oracle Master Scheduling/MRP and Supply Chain Planning loads only sales orders on and within the demand time fence and only forecast entries outside the demand time fence

Load Forecast outside Demand Time Fence Only

Oracle Master Scheduling/MRP and Supply Chain Planning loads all forecast entries outside the demand time fence and ignores forecast entries on and within the demand time fence. Oracle Master Scheduling/MRP and Supply Chain Planning also loads all sales orders from the start date to the cutoff date if you enter All sales orders in the Include field.

Ignore Demand Time Fence

Oracle Master Scheduling/MRP and Supply Chain Planning loads all forecast entries between the start date and the cutoff date and ignores the demand time fence. Oracle Master Scheduling/MRP and Supply Chain Planning also loads all sales orders from the start date to the cutoff date if you enter All sales orders in the Include field.

Sales Orders Only

When you choose to load sales orders into a master schedule, you can manually enter a cutoff date, or use the cutoff date based on the demand time fence. If you use the demand time fence date as the cutoff, Oracle Master Scheduling/MRP and Supply Chain Planning does not consider sales order demand after the demand time fence for an item. If the item has no demand time fence or you ignore the demand time fence, Oracle Master Scheduling/MRP and Supply Chain Planning includes all sales orders up to the cutoff date that you specify. See: Loading a Master Schedule from an Internal Source..

You can specify the following demand time fence options when you load sales orders into a master schedule.

Load Sales Orders Within Demand Time Fence

Oracle Master Scheduling/MRP and Supply Chain Planning loads all sales orders within the demand time fence. Oracle Master Scheduling/MRP and Supply Chain Planning does not include sales orders outside the demand time fence.

Ignore Demand Time Fence

Oracle Master Scheduling/MRP and Supply Chain Planning loads all sales orders ignoring the demand time fence.