Viewing Capacity Information from the Planner Workbench
You can use the Planner Workbench to view capacity information for a plan, as long as you have Oracle Capacity installed.
Note: Depending on your setup, capacity information calculated might include line requirements for discrete jobs and planned orders.
Before you can view capacity information from the Planner Workbench, you must:
To indicate that you want to plan both materials and capacity, check the Plan Capacity check box in the Plan Options window before you run the plan. If the plan is an MPS plan, also assign a Bill of Resource to at least one organization. See: Reviewing or Adding Plan Options.
Note: The Plan Capacity flag is enabled only when CRP is installed.
Launch the plan.
To view capacity information:
1. Navigate to the Planner Workbench.
2. Find the plan for which you want to find capacity information.
3. Click the Resources button.
4. Enter your search criteria in any of the following fields:
6. Enter a value for From and, if necessary, one for To.
7. Optionally, click In Folder and choose the name of the folder in which want to save your Find criteria.
Saving your Find criteria in a folder enables you to use it later.
8. Click Find to find capacity information that matches the search criteria you just entered.
The Resource window appears.
9. Scroll right, if necessary, to see values in the following fields:
Dept/Line: specifies whether the resource is a department or a production line
Resource: the name of the resource
Org: the organization to which the resource belongs; this field only appears if you're looking at a multi-org plan
Owning Dept: the department that owns the resource
Dept Class: the department class associated with the department
Resource Type: the type of resource, such as person, machine, and so on
Resource Group: the group to which the resource belongs
Min Rate: the minimum hourly rate for a production line
Max Rate: the maximum hourly rate for a production line
To view resource requirements for a particular resource:
1. Navigate to the Resource window.
2. Select the resource or resources for which you want to see detailed information.
3. Click the Resource Details button.
The Requirements window appears.
4. Look at the values in the following fields:
Start Date: the beginning date that the department and resource are required
End Date: the ending date that the department and resource are required
Required Hours: the total number of hours required by a repetitive schedule, or the number of hours required by a discrete job or planned order
Schedule Quantity: for discretely manufactured items, the quantity of the item scheduled for the date; for repetitively manufactured items, the total quantity of the item on the schedule
Using Assembly: the assembly that is the source of the demand
Daily Rate: the daily production rate for the repetitive schedule, effective from the schedule start date to the schedule end date
Order Number: the order number that is the source of the demand
Order Type: the type of order that is the source of the demand: Discrete job, Non-standard job, Planned order, or Repetitive Schedule
Source Item: the item that generates the resource requirement
Op Seq: the operation sequence associated with the department and resource
Daily Hours: the number of hours required by a discrete job or planned order
Schedule Start Date: the start date of the demand
Rate End Date: the date on which the repetitive production rate ends
Load Rate: the load rate for the repetitive schedule; the load rate is the daily rate multiplied by the load factor, which is the maximum hourly rate divided by the line speed for a given repetitive assembly and production line
To view available capacity for a particular resource:
1. Navigate to the Resource window.
2. Select the resource for which you want to see available capacity.
3. Click the Availability button.
The Available Resources window appears.
4. Look at the values in the following fields:
From Date: the beginning date that the department and resource are available
To Date: the ending date that the department and resource are available
Max Rate: the maximum hourly rate for a production line
Capacity Units: number of units of a resource available in a department.
Daily Capacity: the number of hours available per day per resource