Typically, you can order components of a planning bill, but not the planning item itself. The planning item is an artificial grouping of products that helps you to improve the accuracy of your forecasting since, generally, the higher the level of aggregation, the more accurate the forecast.
When you load a planning item forecast into another forecast, you can choose to explode the aggregate forecast for the planning item into detailed forecasts for each of the components defined on the planning bill. The forecast quantities exploded to the components are calculated by extending the planning item forecast by the component usages and planning percents defined on the planning bill. You can also choose to explode forecasts when you load a planning item forecast into a master schedule.
Level | Item | BOM Item Type | Planning % |
---|---|---|---|
1 | Training Computer | Planning | |
. 2 | . Laptop Computer | Model | 60% |
. 2 | . Desktop Computer | Model | 20% |
. 2 | . Server Computer | Model | 20% |
Table 1 - 57. Planning Bill of Material for Training Computer (Page 2 of 2) |
The following table illustrates forecast explosion, via the planning bill described in the previous table, for a forecast of 100 Training Computers. The table also illustrates forecast consumption after you place sales order demand for 20 Laptop Computers. Original forecast shows forecast quantities before forecast consumption. Current forecast shows forecast quantities after consumption by sales order demand.
Level | Item | Original Forecast | Current Forecast |
---|---|---|---|
1 | Training Computer | 100 | 100 |
. 2 | . Laptop Computer | 60 | 40 |
. 2 | . Desktop Computer | 20 | 20 |
. 2 | . Server Computer | 20 | 20 |
Table 1 - 58. Forecast Explosion and Forecast Consumption (Page 1 of 1) |
The logic for exploding models and option classes is the same as the logic used to explode planning items.
Level | Item | BOM Item Type | Optional | Planning % |
---|---|---|---|---|
. 2 | . Laptop Computer | Model | No | 60% |
. . 3 | . . Carrying Case | Standard | No | 100% |
. . 3 | . . Keyboard | Standard | No | 100% |
. . 3 | . . CPU | Option Class | No | 100% |
. . 3 | . . Monitor | Option Class | No | 100% |
. . 3 | . . Operating System | Option Class | Yes | 90% |
Table 1 - 59. Model Bill for Laptop Computer (Page 1 of 1) |
Level | Item | BOM Item Type | Optional | Planning % |
---|---|---|---|---|
. . 3 | . . Monitor | Option Class | No | 100% |
. . . 4 | . . . VGA | Option Class | Yes | 70% |
. . . . 5 | . . . . VGA Manual | Standard | No | 100% |
. . . . 5 | . . . . VGA1 | Standard | Yes | 50% |
. . . . 5 | . . . . VGA2 | Standard | Yes | 50% |
. . . 4 | . . . EGA | Option Class | Yes | 30% |
. . . . 5 | . . . . EGA1 | Standard | No | 55% |
. . . . 5 | . . . . EGA2 | Standard | Yes | 45% |
Table 1 - 60. Option Class Bills for Monitor, VGA, and EGA (Page 2 of 2) |
Forecast consumption, forecast explosion, master scheduling, planning, production relief, and shipment relief for predefined configurations behave as they do for any other standard item.
Overview of Forecast Explosion
Overview of Forecast Consumption
Forecast Consumption for Models and Predefined Configurations.