![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|
Previous | Next | Contents | Index | Navigation | Glossary | Library |
When you enter None in the Overwrite field, the planning process does not overwrite any firm planned orders. It does, however, overwrite any suggested planned orders that are not firm.
When you enter Outside planning time fence in the Overwrite field, the planning process overwrites all entries from the current plan, planned and firm planned, outside the planning time fence, and overwrites only planned orders inside the planning time fence. It does not overwrite any firm planned orders within the planning time fence. The planning time fence can be different for each item, so the planning process looks at the planning time fence for each item when choosing what to delete.
When you enter Yes in the Append Planned Orders field, the planning process appends additional planned orders after the last entry on the current material plan to meet any additional demand.
The overwrite and append options work in combinations, as described below.
For example, if an existing material plan has the following orders for an item:
Schedule Date | Quantity | Order Status |
---|---|---|
01-FEB | 100 | Planned |
08-FEB | 200 | MRP firm planned |
15-FEB | 300 | Planned |
Table 1 - 31. MRP Plan (Page 1 of 1) |
And the following MDS is used to plan the material plan using All in the Overwrite field and Yes in the Append Planned Orders field:
Schedule Date | Quantity |
---|---|
02-FEB | 110 |
09-FEB | 220 |
16-FEB | 330 |
Table 1 - 32. MDS Schedule (Page 1 of 1) |
Then the resulting material plan would have the following suggestions for planned orders:
Schedule Date | Quantity | Order Status |
---|---|---|
02-FEB | 110 | Planned |
09-FEB | 220 | Planned |
16-FEB | 330 | Planned |
Table 1 - 33. Resulting MRP Plan (Page 1 of 1) |
The planning process always suggests planned orders. You can change planned orders to a firm status using the Items window in the Planner Workbench.
Attention: If an item has no time fence specified and this option is chosen, all planned and firm planned orders are overwritten.
For example, if an existing MRP has the following orders for an item:
Schedule Date | Quantity | Order Status |
---|---|---|
01-FEB | 100 | Planned |
08-FEB | 200 | MRP firm planned |
15-FEB | 300 | Planned |
Table 1 - 34. MRP Plan (Page 1 of 1) |
And the following MDS is used to plan the MRP using Outside Planning Time Fence in the Overwrite field and Yes in the Append Planned Orders field:
Schedule Date | Quantity |
---|---|
02-FEB | 110 |
09-FEB | 220 |
16-FEB | 330 |
Table 1 - 35. MDS Schedule (Page 1 of 1) |
Then the resulting material plan would have the following suggestions for planned orders, assuming the planning time fence is 05-FEB:
Schedule Date | Quantity | Order Status |
---|---|---|
05-FEB | 110 | Planned |
09-FEB | 220 | Planned |
16-FEB | 330 | Planned |
Table 1 - 36. Resulting MRP Plan (Page 1 of 1) |
Since the entry on 01-FEB is not firmed, the MRP planning process overwrites this entry. If it was firmed, the process would not overwrite the entry. The additional demand from the MDS of 110 on 02-FEB was appended on the planning time fence date of 05-FEB. The MRP firm planned order on 08-FEB was deleted because it falls outside the planning time fence of 05-FEB.
The planning process always suggests planned orders. You can change planned orders to a MRP firm status using the Items window in the Planner Workbench.
For example, if an existing MRP has the following suggested planned orders for an item:
Schedule Date | Quantity | Order Status |
---|---|---|
01-FEB | 100 | Planned |
08-FEB | 200 | MRP firm planned |
15-FEB | 300 | Planned |
Table 1 - 37. MRP Plan (Page 1 of 1) |
And the following MDS is used to plan the MRP using None in the Overwrite field and Yes in the Append Planned Orders field:
Schedule Date | Quantity |
---|---|
02-FEB | 110 |
09-FEB | 220 |
16-FEB | 330 |
Table 1 - 38. MDS Schedule (Page 1 of 1) |
Then the resulting material plan would have the following suggestions for planned orders assuming the planning time fence is 05-FEB:
Schedule Date | Quantity | Order Status |
---|---|---|
05-FEB | 110 | Planned |
08-FEB | 200 | MRP firm planned |
09-FEB | 20 | Planned |
16-FEB | 330 | Planned |
Table 1 - 39. Resulting MRP Plan (Page 2 of 2) |
The firm order on 08-FEB remains on the MRP since the overwrite is None. However, the planned entries are deleted. Although additional demand exists on the MDS, no planned orders are suggested until the planning time fence (on 05-FEB). The MDS demand of 110 on 02-FEB was satisfied by a new planned order for 110 on 05-FEB. The demand for 220 on 09-FEB was partially met by the firm MRP planned order on 08-FEB. Thus an additional planned order was suggested on 09-FEB for 20 to meet the MDS demand of 220. A suggested planned order was created on 16-FEB for 330 to meet the demand from the MDS on 16-FEB.
For example, if an existing material plan has the following orders:
Schedule Date | Quantity | Order Status |
---|---|---|
01-FEB | 100 | Planned |
08-FEB | 200 | MRP firm planned |
15-FEB | 300 | Planned |
Table 1 - 40. MRP Plan (Page 1 of 1) |
And the following MDS is used to plan the MRP using None in the Overwrite field and No in the Append Planned Orders field:
Schedule Date | Quantity |
---|---|
02-FEB | 110 |
09-FEB | 220 |
16-FEB | 330 |
Table 1 - 41. MDS Schedule (Page 1 of 1) |
Then the resulting MRP would have the following suggestions for planned orders:
Schedule Date | Quantity | Order Status |
---|---|---|
08-FEB | 200 | MRP firm planned |
Table 1 - 42. Resulting MRP Plan (Page 1 of 1) |
The reason the additional demand from 02-FEB, 09-FEB, and 16-FEB was not planned for is because with the Overwrite None and Do Not Append Planned Orders, you choose not to overwrite firm planned orders nor create new planned orders to meet additional demand. In this case, the projected quantity on hand would go negative since no planned orders were suggested to meet the additional demand. The material planner can use on-line inquiries and reports with exception messages to identify material shortages.
Previous | Next | Contents | Index | Navigation | Glossary | Library |