Deleting Resource Requirements
You can delete resource requirements as you update operations. If you delete an operation, the resources associated with it are automatically deleted.
To delete resource requirements:
1. Navigate to the Operations window.
2. Select the operation Sequence.
The operation Sequence specifies from which operation the resource is to be deleted.
4. In the Main alternative region of the Resource Requirements window, select or enter the resource Sequence number.
5. Select the resource Name.
You can delete a resource requirement regardless of the status of the job or repetitive schedule. You cannot delete a resource that has been charged at an operation (applied quantity exists) or that has pending resource transactions.
If you delete an operation from a job or repetitive schedule, you may want to reschedule the job or repetitive schedule to correctly reflect the start and completion dates.
You cannot delete a PO Move or PO Receipt resources or the operations they are assigned to if purchase requisitions (either approved or unapproved) or purchase orders exist for these resources.
6. Choose Delete Record from the Edit Menu.
See Also
Adding and Updating Operations
Deleting Operations
Adding and Updating Resource Requirements
Overview of Resource Requirements