Repetitive Routing Sheet
The Repetitive Routing Sheet lists operations and associated resources and material requirements for schedules with a status of Unreleased, Released, On Hold, or Complete. You can use the report as a traveler to report production against repetitive schedules on the shop floor. The system displays repetitive assemblies and production lines in alphanumeric order. For each repetitive assembly/line, the system prints schedules ordered by first unit start date and followed by their operations, resources, instructions and requirements.
Report Submission
In the Submit Requests window, select Repetitive Routing Sheet in the Name field.
Report Parameters
Assembly
Select a repetitive assembly. If you do not select an assembly, the system lists routing information for all schedules defined for the line selected.
Line
Select a production line. If you do not select a line, the system displays routing information for all schedules defined for the assembly selected.
First Unit Start
Dates From/To
To restrict the report to a range of first unit start dates, select a beginning and an ending date.
See Also
Overview of Repetitive Manufacturing
Submitting a Request