Siebel Field Service Guide > Release Manager > Quality Assurance End-User Procedures for Release Manager >

Recording a Test Pass and Linking a Test Plan


When a QA test plan is complete and is associated with a test strategy, tests can be done against it. Because test plans are linked to their features in Release Manager, QA managers can focus their teams' efforts on those test plans that are associated with the greatest number of new features. As each test is executed, QA testers record the results in Release Manager. Each test pass is linked to the test plan that it executes.

To record a test pass and link a test plan

  1. Navigate to Site Map > Release > QA Tests.
  2. Add a new test record.
  3. In the Test Plan field, select the test plan on which the test pass is based.
  4. Complete the other fields, as needed. Some fields are described in the following table.
  5. Field
    Comments
    Build
    Product prototype that was tested.
    Client OS
    Type of operating system running on the client test machine.
    Client Type
    Type of test machine used by the tester.
    Cover %
    Portion of the test plan that was executed (covered) by this test.
    Database
    Type of database running in the test environment.
    Date
    Date when the test was conducted.
    Interactivity
    Specifies whether the test is either in High Interactivity Mode or in Standard Interactivity Mode.
    Pass %
    Portion of the test plan that passed this test.
    Release
    Name or number of the product release with which the test is associated.
    Server OS
    Type of operating system running on the server machine in the test environment.
    Status
    Stability of the prototype as assessed by the tester during that test.
    Tester
    Individuals associated with the test. The individual who conducted the test should be set as Primary.
    Type
    Type of test that was conducted.