Siebel Professional Services Automation Guide > Expense Reporting >

Moving Multiple Expense Items to Another Project


It is also possible to move multiple expense items from one project to another at one time, but this requires that end users know the exact value they want to place in the Project field. The following procedure explains how to do this.

To move multiple expense items from one project to another

  1. In the Time and Expense list, hold down the CTRL key as you select multiple items to be moved from one project to another.
  2. In the Time and Expense list, click the menu button and select Change Records.
  3. In the First Field to Change section of the Change Records dialog box, select Projects from the Field drop-down list.
  4. In the First Field to Change section of the Change Records dialog box, enter the exact value for the new project in the Value field.
  5. Click OK.

 Siebel Professional Services Automation Guide 
 Published: 18 April 2003