PurgePWCData purges PWC (job and task instance) data from the database with a date processed that falls outside the range you specify here. If you are running report jobs, these files can grow rapidly.
You have the option not to purge PWC data when you run the Purge App job.
If you specify a number of days to purge prior to of less than 7, Purge App only purges job instances with Done status.
|
PurgePWCData Task Configuration | ||
|
Field |
What to enter/select | |
|
Purge Prior to (Number of Days) |
Specify one of the following values to determine what to purge: | |
|
|
0 |
Purges all information up to midnight of the current date |
|
|
1 |
Purges all information up to midnight of the previous day |
|
|
>1 |
Purges all information up to midnight of the (relative) day specified (limit is 3650 days, or ten years) |
|
|
-1 |
Do not purge. Choose this option if you do not want to purge this task data from the Index table when you run the Purge App job. |