Distributing Costs to Budget Detail Rows

This chapter provides an overview of cost and revenue budget generation, lists prerequisites, and discusses how to distribute costs to budget detail rows.

Click to jump to parent topicUnderstanding Cost and Revenue Budget Generation

PeopleSoft Program Management enables you to generate project cost and revenue budget details from the amounts defined on the Resources by Activity page.

This section discusses:

Note. This feature uses the PeopleSoft Project Costing Budgeting functionality.

See Budgeting Project Costs and Revenue.

Click to jump to top of pageClick to jump to parent topicBudget Generation Process Flow

You can create a detail budget plan in these ways:

This chapter discusses creating a detail budget plan from resources defined on the Resources by Activity page.

If a project request is not required, you can manually create a project using the Project General component (PROJECT_GENERAL). If a project request is used, the funding manager may request a detailed budget plan for the project request. In this case, the funding manager sets the project request to a status of Costing, and the system generates a project.

Use the Resources by Activity page on the project to identify the projected resources for the project. This information includes both cost and revenue information for the projected resources.

After project managers identify the resources on the Resources by Activity page, they can create budget details using project the Budget Plan component (PC_BUD_GENERAL).

Click to jump to top of pageClick to jump to parent topicBudget Details Generation

After a project manager defines the resources needed in the Resources by Activity page, you can use the Get Plan feature to load the estimates into a budget plan. Use these steps to load resource estimates into a budget plan:

  1. Create and save a budget plan for the project cost or revenue budgets.

    Set the status of the cost and revenue plan IDs to Active.

  2. Click the Get Plan button on the appropriate Plan ID line to retrieve the resource cost or revenue estimates from the Resources by Activity page and initiate the Distribute Costs to Budgets Application Engine process (PGM_SPREAD).

    The plan ID line must have a status of Active to retrieve resource estimates. The project must have a processing status of Pending, Active or Template to retrieve resource estimates. The Get Plan feature does not process resource cost or revenue estimates from the Resources by Activity page that occur prior to the budget plan's start date.

    The Distribute Costs to Budgets process creates budget detail lines for each activity using the estimates defined in the Resources by Activity page.

  3. Review the Distribute Activity Resource Amounts page if available, and update the information if necessary.

If you add or delete resources on the Resources by Activity page after you created a detail budget, depending on the results you want, you can:

If the project is part of a program, you can roll project budget details up to the program budget.

See Budgeting for Programs.

Click to jump to top of pageClick to jump to parent topicDistribution of Activity Resource Amounts to Budget Details

The system uses these rules to determine how to distribute activity resource amounts:

When the Get Plan process distributes amounts from the Resources by Activity page according to the percentage distribution of the general ledger business unit and department ID combination, each row from the Resources by Activity page generates a separate budget detail row for each unique general ledger business unit and department ID combination.

If the general ledger business unit and department ID values are defined in the Budget Item ChartFields, they are overridden by the values from the Project Request - Costing page or Distribute Resource Activity Amounts page. All other ChartField values defined for the budget item are carried over to the budget detail row.

Note. If you select the Allow Get Plan Distribution By Department option on the Installation Options - Project Costing page, you must use the Distribute Activity Resource Amounts page to define the general ledger business unit and department ID when using the Get Plan feature for all projects that are not associated with a project request.

Click to jump to top of pageClick to jump to parent topicDistribution of Resource Amounts Across Budget Periods

After you generate separate budget detail rows from the Resources by Activity amounts, the Get Plan process distributes those values across budget periods in the budget plan. The system distributes the amounts using one of these methods:

Click to jump to top of pageClick to jump to parent topicCurrency Conversion

You can enter activity amounts in different currencies. When you run the Distribute Costs to Budgets Application Engine process, the system generates and converts the budget detail amounts to the currency code specified for the budget plan.

Click to jump to parent topicPrerequisites

To enable users to choose the general ledger business unit and department ID for budget details rows, you must activate the Allow Get Plan Distribution by Department option on the Installation Options - Project Costing page.

See Defining Project Costing Integration Installation Options.

Click to jump to parent topicEntering Distribute Costs to Budget Detail Rows

This section discusses how to:

Click to jump to top of pageClick to jump to parent topicPages Used to Distribute Costs to Budget Detail Rows

Page Name

Object Name

Navigation

Usage

Installation Options - Project Costing

INSTALLATION_PC

Set Up Financials/Supply Chain, Install, Installation Options, Project Costing

Enable users to choose the general ledger business unit and department ID distribution for budget detail rows.

See Defining Project Costing Integration Installation Options.

Budget Plan

PC_BUD_GENERAL

Project Costing, Budgeting, Budget Plan, Budget Plan

Create and view all budget plans associated with a project, and initiate the Get Plan feature to populate budget detail rows.

Distribute Activity Resource Amounts

PGM_COST_PCT

Click the Get Plan button on the Budget Plan page when the Allow Get Plan Distribution by Department option on the Installation Options - Project Costing is enabled.

Enter general ledger business units, department IDs, and distribution percents for the system to use to distribute resource amounts to budget detail rows.

Budget Detail

PC_BUD_DETAIL

Click the Budget Detail icon on the Budget Plan page.

View budget detail rows that were created by the Get Plan feature.

Click to jump to top of pageClick to jump to parent topicGenerating Budget Details from Activity Resource Amounts

Access the Budget Plan page.

Click the Get Plan button on an active budget plan row to launch the Distribute Costs to Budgets process. This process creates budget detail rows based on activity resource amounts. If the budget plan has a budget type of Cost, the system uses the cost amounts from the Resources by Activity page on the detail budget rows. If the budget plan has a budget type of Revenue, the system uses the bill amounts from the Resources by Activity page on the detail budget rows.

The Distribute Costs to Budgets process completes one of these actions:

See Budgeting Project Costs and Revenue.

Click to jump to top of pageClick to jump to parent topicEntering General Ledger Business Unit and Department Values for Budget Details

Access the Distribute Activity Resource Amounts page.

GL Business Unit (general ledger business unit)

Enter the general ledger business unit to be used on budget detail lines for this project.

Department

Enter the department ID to be used on budget detail lines for this project.

Distribution Percent (%)

Enter the percentage for each general ledger business unit and department combination. The sum of the distribution percents must equal 100 percent.

Note. This page does not appear if the project is associated with a project request or if the Allow Get Plan Distribution by Department check box is not selected on the Installation Options - Project Costing page.