This chapter provides an overview of independently created commitments and discusses how to:
Create lot commitments from extra purchase orders.
Create lot commitments from external purchase orders.
Understanding Independently Created CommitmentsIn the JD Edwards EnterpriseOne Homebuilder Management system, the Lot Start process creates the majority of on-site commitments by using a combination of bids and takeoffs to generate purchase orders in the JD Edwards EnterpriseOne Procurement system. However, you might need to create commitments independent of the Lot Start process. For these situations, select an option to manually create commitments:
Create lot commitments from extra purchase orders.
Create lot commitments from external purchase orders.
Create non-lot-related commitments by creating subcontracts in the JD Edwards EnterpriseOne Procurement system.
Use subcontracts for all non-lot-related commitments, such as due diligence, engineering, land development, and potential marketing costs.
Creating Lot Commitments from Extra Purchase Orders
This section provides an overview of extra purchase orders and discusses how to:
Set processing options for Extra Purchase Order Entry (P44H703).
Create lot commitments in the F44H711 workfile from extra purchase orders.

Understanding Extra Purchase OrdersIn many instances, you need to purchase additional materials for a lot. These extra purchase orders are often referred to as field purchase orders because they originate at the construction site. Extra purchase orders are used for commitments for lots only. You can use the Extra Purchase Orders program (P44H703) to create these extra purchase orders. You can set processing options for the P44H703 program to allow line changes or additions to a selected contract.
The P44H703 program provides:
Flexible data entry.
Access to pricing information.
A separate source document type (OP) for extra purchase orders.
When you create extra purchase orders, the system updates the After Start Purchasing table (F44H711P). When you create commitments based on the extra purchase orders, the system updates the Lot Start Workfile (F44H711). Purchase orders in the F44H711 workfile are available to all JD Edwards EnterpriseOne Homebuilder Management system functions, including cost analysis, commitment processing, and accounts payable processing.
The system performs account validations on a record before it is updated from the F44H711P table to the F44H711 workfile. If you revise a contract, these restrictions apply:
An item must exist in the Item Master (F4101) and Item Master Homebuilder Extension (F44H4101) tables.
The last status of a committed line from the Purchase Order Detail File (F4311) must be less than the defined status of the order.
You specify whether to allow revisions in the processing option Allow Lot Start Workfile Revisions in the Extra Purchase Order Entry program.
You cannot make changes to the account if payments have been processed on the committed line.
The commitment posting status must be blank or P (posted).
If the status is posted, the previous restrictions apply.
Calculations and data retrieval are based on values on the Work with After Start Purchasing form:
The Unit Cost field must be blank for the system to retrieve new or adjusted pricing.
If this field is not blank, the system uses the current unit cost and the quantity entered to calculate the extended amount.
If you change the Item Number field, the system retrieves the corresponding short and third item numbers.
The taxable status is based on the community and then the vendor.
However, the new or adjusted tax amount is not recalculated until you run the Generate Homebuilder Commitments program (R44H7113) again.
If you change the Cost Code or Cost Type fields, the system retrieves the corresponding account ID (AID), long account number (ANI), and account description from the Account Master table (F0901).
If you enter a value in the Option Number field, the option availability is validated and the takeoff process retrieves the pricing.
If an assigned supplier pricing is not found in the Material Item Pricing table (F44H603), the system retrieves the default pricing from the Item Master Homebuilder Extension table (F44H4101).

Forms Used to Create Lot Commitments from Extra Purchase Orders
|
Form Name |
FormID |
Navigation |
Usage |
|
Work with After Start Purchasing |
W44H703A |
After Start Commitments and Costing (G44H24), Extra Purchase Order Entry |
Review extra purchase orders. |
|
After Start Purchasing Maintenance |
W44H703B |
On the Work with After Start Purchasing form, select a record and click Select. |
Note. If you upload records from an external system, you can access those records on the After Start Purchasing Maintenance form. |
|
Work With Lot Start Workfile |
W44H711A |
On the Work with After Start Purchasing form, select Lot Start Workfile from the Form menu. |
Review the extra purchase orders. |
|
Lot Start Workfile Revisions |
W44H703D |
On the Work With Lot Start Workfile form, select a record and click Select. |
Revise generated lot start workfiles. Note. You can review the purchase order detail that corresponds to a record when you select PO Detail from the Lot Start Workfile Revisions form. |

Setting Processing Options for Extra Purchase Order Entry (P44H703)Processing options enable you to specify the default processing for programs and reports.
Defaults
The values that you enter for the processing options on this tab appear in fields on the After Start Purchasing Maintenance form.
|
1. Cost Type |
Specify the default cost type. |
|
2. Document Type |
Specify a code from user-defined code (UDC) table 00/DT that identifies the default document type. |
|
3. Homebuilder Area |
Specify a code from UDC 00/05 that identifies the default area. |
Process
|
1. Allow Cost Type Changes |
Specify whether to allow cost type changes. Values are: Blank: Do not allow. 1: Allow. |
|
2. Allow Item Entry |
Specify whether to allow an item to be added to a purchase order. Values are: Blank: Do not allow. 1: Allow. |
|
3. Create Budget |
Specify whether to create a budget. Values are: Blank: Do not create. The Budget Post Status field is set to 2 for the record that the system created in the Lot Start Workfile (F44H711). 1: Create. The Budget Post Status field is set to 0 for the record that the system created in the F44H711 workfile. |
|
4. Ignore Date Warning Error |
Specify whether the system allows you to ignore warning messages when you select Create Workfile from the Form menu on the Work With After Start Purchasing form. Values are: Blank: Do not ignore. 1: Ignore. |
|
5. Allow Lot Start Workfile (F44H711) Revisions |
Specify whether the system allows revisions to purchase orders that exist in the Lot Start Workfile (F44H711). Values are: Blank: Allow. 1: Do not allow. Note. If you leave this processing option blank, you can change purchase order lines that have been committed as long as the status of the order is less than the defined status. If the status of the order is less than the defined status, purchase order lines in the Purchase Order Detail File (F4311) cannot be changed if the item has not been partially or fully received or vouchered. |
|
6. F4311 Detail Line Protection Status |
Enter a code from UDC 40/AT that specifies the last status code at which revisions can be made to a purchase order line that exists in the F4311 table. If you leave this processing option blank, the system uses the default status 999. |
|
7. Discount Type |
Specify the discount type that the system uses when the extended price is calculated for an item. Values are: Blank: None 1: Standard. 2: Model. |
Versions
|
1. Vendor Assignment Outbound Notification (P44H9902) Version |
Specify the version of the P44H9902 program to use when scheduling is enabled. If you leave this processing option blank, the system uses the ZJDE0001 version. |
|
2. Purchase Orders (P4310) Version |
Specify the version of the P4310 program to use when you select PO Detail from the Row menu in the Lot Start Workfile Revisions form. If you leave this processing option blank, the system uses the ZJDE0015 version. |
|
3. Lot Start Workfile Review (P44H711) Version |
Specify the version of the P44H711 program to use from the Work With Lot Start Workfile form. If you leave this processing option blank, the system uses the ZJDE0001 version. |

Creating Lot Commitments in the F44H711 Workfile from Extra Purchase OrdersAccess the After Start Purchasing Maintenance form.
After completing this form, return to the Work with After Start Purchasing form, select a record, and select Create Workfile from the Row menu to create lot commitments.
The steps for creating lot commitments from extra purchase orders are the same as those for creating commitments manually.
|
Doc Number |
Leave this field blank so that the system assigns the next number. |
|
Quantity Ordered |
Enter the quantity of units affected by this extra purchase order. |
|
Purch Report Code 1 (purchasing report code 1) through Purch Report Code 5 (purchasing report code 5) |
Enter reporting codes from UDC 41/P1–UDC 41/P5 that differentiate segments of inventory in a meaningful way for buying department personnel. Depending on the nature of the inventory, this code might be used to establish attributes, such as color, country of origin, or primary content (for example, brass or wood). Reporting code 1 is predefined as a purchasing code for commodity class. |
Creating Lot Commitments from External Purchase Orders
This section provides an overview of external purchase orders and discusses how to create lot commitments in the F44H711 workfile from external purchase orders

Understanding External Purchase Orders
You can upload purchase orders from an external scheduling or purchasing system into the JD Edwards EnterpriseOne Homebuilder Management system. For example, superintendents might enter field purchase orders in a third-party system that captures basic order information. You can upload these purchase orders into the JD Edwards EnterpriseOne Homebuilder Management system and create commitments based on the external purchase orders.
JD Edwards EnterpriseOne Homebuilder Management provides a table to receive purchase order information from external systems. You upload the data from the external system to the After Start Purchasing table (F44H711P). The system does not validate the purchase order information before it updates the F44H711P table. After you verify that the purchase order information on the After Start Purchasing Maintenance form is complete and accurate, you can upload the external purchase orders to the Lot Start Workfile (F44H711). The information then becomes available to all JD Edwards EnterpriseOne Homebuilder Management system functions, including cost analysis, commitment processing, and accounts payable processing.

Creating Lot Commitments in the F44H711 Workfile from External Purchase OrdersAccess the Work with After Start Purchasing form.
To create lot commitments from external purchase orders:
Click Find to locate the external purchase orders in which to create commitments in the F44H711 workfile.
Select one or multiple purchase orders, and then select Create Workfile from the Row menu.
When you select a purchase order, the system uploads all order lines associated with that purchase order. You do not need to choose all of the individual lines of an order.
The system will display any errors in the external purchase orders before updating the F44H711 workfile.
Select any records with errors, and click Select.
Correct any errors on the After Start Purchasing Maintenance form, and click OK.
On the Work with After Start Purchasing form, select Create Workfile from the Row menu.