Appendix: JD Edwards EnterpriseOne Work Orders Reports

This appendix provides an overview of work order reports and enables you to:

Click to jump to parent topicUnderstanding Work Order Reports

You can print work order information in a variety of formats to help you manage work orders and work order projects.

You can print cost reports to review the costs associated with work orders, such as estimated and actual hours and costs. You can also review details about the cost transactions that you charge to work orders.

Project management reports help you manage work order projects and schedules. These reports include this information:

Number of hours remaining or the number of hours charged over the original estimate for each work order in a project

You can print multiple work orders by using report selection criteria to specify the work orders that you want to print. To access the Work Order Print program (R48415), select the Work Order Print on the Work Order Processing menu (G4811).

You print work orders when you need a hard copy of a group of work orders. When you print work orders, you use data selections to specify which work orders to print or suppress. You then use processing options to specify the information that you want to print, such as whether to suppress dates associated with information about a work order record type, suppress estimated hours associated with work orders, or print equipment messages associated with a piece of equipment on the work order. In addition, you can enter record types to be printed with a work order. You also can specify whether the system changes the status of the work orders at the same time that it prints them.

Click to jump to parent topicWork Order Reports: A to Z

This table lists the work order reports, sorted alphanumerically by report ID:

Report ID and Report Name

Description

Navigation

R48492

Detailed Task Description

Lists the work orders that are included in a project.

Simple Project Management (G4812), Detailed Task Description

R48495

Project Status Summary

Review summary and detailed status information about all of the projects that are assigned to a specific manager.

Simple Project Management (G4812), Print Project Status Summary

R48496

Work Order Summary

Review summary information for tracking and comparing the progress of selected work orders. You can view work order summaries for the Work Orders system and the Capital Asset Management system.

Work Order Processing (G4811), Print Work Order Summary

Work Order menu (G1316), Print WO Status Summary

R48497

Cost Summary

Review and analyze the costs and individual cost transactions that are associated with work orders. You can view cost summaries for the Work Orders system and the Capital Asset Management system.

Work Order Processing (G4811), Work Order Cost Summary

Work Order menu (G1316), Print WO Cost Summary

R48498

Cost Detail

Review detailed information about the costs that you charge to work orders. You can view cost details for the Work Orders system and the Capital Asset Management system.

Work Order Processing (G4811), Cost Detail

Work Order menu (G1316), Print WO Cost Detail

Click to jump to parent topicSelected Work Order Reports

Some reports include a more detailed description, as well as information about processing options. These reports are listed alphanumerically by report ID in this appendix.

Click to jump to top of pageClick to jump to parent topicR48492 - Printing the Detailed Task Description

The Detailed Task Description report lists the work orders that are included in a project. For each work order, the report includes:

Click to jump to top of pageClick to jump to parent topicR48495 - Printing the Project Status Summary

The Project Status Summary report contains summary and detailed status information about all of the projects that are assigned to a specific manager, including:

The report also lists a summary of activities for a manager by the work order status, type, priority, and all category codes.

Click to jump to top of pageClick to jump to parent topicProcessing Options for Print Project Status Summary (R48495)

Use this processing option to supply the default value for Print Project Status Summary.

Print

1. Print Ledger Type

Enter a user defined code (09/LT) that specifies the type of ledger, such as AA (Actual Amounts), BA (Budget Amount), or AU (Actual Units). You can set up multiple, concurrent accounting ledgers within the general ledger to establish an audit trail for all transactions.

If you leave this processing option blank, the system prints all ledger types.

Click to jump to top of pageClick to jump to parent topicR48496 - Printing the Work Order Summary Report

Print the Print Work Order Summary Print report (R48496) to review summary information for tracking and comparing the progress of selected work orders. The report includes:

The system retrieves information for this report from these tables:

Click to jump to top of pageClick to jump to parent topicProcessing Options for Work Order Summary Print (R48496)

Use these processing options to supply the default values for the Work Order Summary Print.

Print

1. Equipment Number Format

Specify how the system displays the equipment number. Values are:

Blank: Do not display the equipment number.

1: Display the asset number.

2: Display the unit number.

3: Display the serial number.

Defaults

1. Ledger Type

Specify the ledger type to be used when selecting records for actual hours from the Account Ledger (F0911) file. Enter a value from UDC 09/LT (Ledger Type). If you leave this processing option blank, the system uses ledger type AA.

Click to jump to top of pageClick to jump to parent topicR48497 - Print Cost Summary Reports

You can print cost summary information for work orders and use processing options to enter the date range for the report. This report includes:

The system retrieves information for this report from these tables:

Click to jump to top of pageClick to jump to parent topicProcessing Options for Print Work Order Cost Summary (R48497)

Use these processing options to supply the default values for Print Work Order Cost Summary.

Process

1. Date Rangea. From Date:

Specify the From Date that the system uses when including costs on this report. Use this processing option in conjunction with the Thru Date processing option.

If you leave this date blank, the system includes all costs with GL dates up to the Thru Date.

If you leave both the from and thru dates blank, the system includes all costs regardless of their GL dates.

1. Date Rangeb. Thru Date:

Specify the Thru Date. that the system uses when including costs on this report. Use this processing option in conjunction with the From Date processing option.

If you leave this date blank, the system includes all costs with GL dates from the From Date forward.

If you leave both the from and thru dates blank, the system includes all costs regardless of their GL dates.

Defaults

1. Ledger Type

Specify the ledger type to be used when selecting records for actual hours and amounts from the Account Ledger (F0911) file. Enter a value from UDC 09/LT (Ledger Type). If you leave this processing option blank, the system uses ledger type AA.

Click to jump to top of pageClick to jump to parent topicR48498 - Printing the Cost Detail Report

Print the Print WO Cost Detail report (R48498) to review detailed information about the costs that you charge to work orders. You use processing options to specify the date range for the report. The report includes:

The system retrieves information for this report from these tables:

Click to jump to top of pageClick to jump to parent topicProcessing Options for Print Work Order Cost Detail (R48498)

Use these processing options to supply the default values for Print Work Order Cost Detail.

Process

1. Date Rangea. From Date:

Specify the From Date that the system uses when including costs on this report. Use this processing option in conjunction with the Thru Date processing option.

If you leave this date blank, the system includes all costs with GL dates up to the Thru Date.

If you leave both the from and thru dates blank, the system includes all costs regardless of their GL dates.

1. Date Rangeb. Thru Date:

Specify the Thru Date. that the system uses when including costs on this report. Use this processing option in conjunction with the From Date processing option.

If you leave this date blank, the system includes all costs with GL dates from the From Date forward.

If you leave both the from and thru dates blank, the system includes all costs regardless of their GL dates.

Defaults

1. Ledger Type

Specify the ledger type to be used when selecting records for actual hours and amounts from the Account Ledger (F0911) file. Enter a value from UDC 09/LT (Ledger Type). If you leave this processing option blank, the system uses ledger type AA.