Feeder Line Synchronization

Feeder Line Synchronization

In manufacturing environments where many types of items are produced, the total amount for different configurations of a product may not be sufficient to support a Kanban replenishment system. Oracle Flow Manufacturing resolves this situation by enabling you to create schedules for lines that are directly derived from parent assembly line schedules. These feeder lines use sequence information from the parent assembly schedules so that you can synchronize the higher and sub-assembly material with production.

The feeder line synchronization program calculates the date and time the subassembly is delivered to the particular line operation. This date is then be used as the completion date for the subassembly line. The completion date of the feeder line flow schedule is calculated as the difference between the parent assembly's scheduled completion date and the sum of the operation times. This is the sum of the operation times from the consuming operation to the end of the parent line.

Note: The basis type of the subassembly is considered in the calculation. See: Fixed Component Usage

The start time for the subassembly is calculated by subtracting the lead time from the completion date and time. Lead time is obtained from fixed lead time and variable lead time on the organization item. This allows you to synchronize subassembly lines to deliver product exactly when needed by the main line.

You cannot create new synchronized schedules if corresponding schedules already exist on the feeder line. You also cannot re-synchronize rolled schedules. This eliminates potentially creating over production of the subassembly.

Prerequisites

To create flow schedules that synchronize feeder lines with parent assembly lines

  1. Navigate to the Feeder Line Synchronization window.

    The Parameters window appears.

  2. Select a parent line or range of Lines From and To.

    the picture is described in the document text

  3. Select a range of Dates From and To.

    This is the date range of the start dates of the parent assembly schedule; it is used to determine which parent schedules are synchronized.

  4. Choose OK.

  5. Choose Submit Request.