Managing Plans

Workbench Actions

Each simulation plan goes through this life cycle.

Action Plan State
Create Plan Created
Launch Plan Successfully launched
Load Plan Loaded in memory
Close Plan Not in memory; closed
Save Plan Saved to database from memory
Delete Plan Delete plan from memory and database

Use the actions to act against plans. You find links to the actions in the Plan Actions section of the navigator in the Plan inputs tab.

For each action, this tells you:

You cannot perform all actions on all plans. For example:

Change History

Use this action to view the changes that all planners have made to a plan.

It shows the entire change log for the plan in a pop up window.

Each change log entry shows the entity, who made the change, when they made the change, and the data values before and after the change.

Clear Comparisons

Use this action after you have done a plan comparison and you want to remove the comparison data.

It removes all comparison plan data and returns all tabs to the base plan data.

Close Plan

Use this action to close a plan that you have loaded into memory.

Copy Plan

Use this action to make copies of plans to save or simulate.

Rapid Planning Plans

It opens the copy plan pop-up page with current plan as From Plan. Select Plan Type Rapid Planning. Once you confirm the copy, the new plan appears in the list of plans.

Baseline Plans from Oracle Advanced Supply Chain Planning

Select Plan Type ASCP. See Simulating Plans from Oracle Advanced Supply Chain Planning, Copy Plan.

Compare Plan

Use this action to compare plans.

It pops up a list of all plans and you select one plan.

If you have any of these tabs open, they are subject to the comparison between the base plan and the comparison plan:

A tab that is subject to comparison typically:

Create Plan

Use this action to create plans.

It opens the plan definition and options page in a pop-up window with an empty plan name and default values. Once you create a plan, you can see it in the list of plans.

Define Incremental Replan Scope

Use plan action Define Incremental Replan Scope to specify the scope of the replans by:

Supply Selection Criteria

You can limit by these selection criteria and conditions:

These criteria are like OR searches. If a supply meets any criterion and condition, the action selects it.

When you select condition Saved Selection Equals, the list that you see does not include dynamic lists, for example top ten lists.

If you select Include pegged upstream supplies, the action selects all supplies that peg down to the selected supplies.

If you select Include pegged downstream supplies, the action selects all supplies that peg up to the selected supplies.

You can also use search attribute Updated in Plan = Yes to find all of the entities that the plan updated.

Incremental Planning Mode

Freeze existing plan / Replan new demands only: The planning process freezes the supplies and demands in the prior run of the plan and plans to meet demands that you adds since then.

Freeze Selected Supplies / Replan all demands: The planning process replans all demands but does not replan the supplies that you select. It can make planned orders and recommend reschedule for supplies that you did not select.

Freeze All Except Selected Supplies / Replan all demands: The planning process replans all demands but does not replan the supplies that you did not select. It can make planned orders and recommend reschedule for supplies that you select.

Firm Supplies

For firm supplies, the process makes dependent component requirements and resource requirements firm as well.

Delete Plan

Use this action to delete plans.

This action purges the plan from memory and the database and is irrevocable.

When you run a copied plan, the planning solver needs its base plan base plan. If you delete a base plan, all plans copied from it are invalid.

If you delete a plan that is a simulation from a baseline Oracle Advanced Supply Chain Planning plan, you receive a warning.

Launch Plan

Use this link to re-plan plans.

It opens a launch plan page in a pop-up window.

Field Plan shows that plan that you currently have selected and you can select another one instead.

If you don’t have any plan selected, field Plan is blank and you can select one

You select :

The progress bar shows the progress of the planning solver.

Schedule Plan in the Future

When you are signed in under the Oracle Supply Chain Simulation Planner, you can schedule a Rapid Planning Plan in the future.

To schedule a Oracle Rapid Planning Plan in the Future:

  1. Sign in under the Oracle Supply Chain Simulation Planner responsibility.

  2. Under the Other heading, click Request.

    The Submit Request form pop-up window appears.

    the picture is described in the document text

  3. Click the Name field.

You can select the name of the concurrent request, Launch Simulation Planner.

The Parameter screen appears.

the picture is described in the document text

Save Options

Save options can be one of three possible values:

  1. Save and Close Plan. This option ensures that the executed Rapid Planning plan, which was run on a defined schedule, saves and closes the plan. This guarantees that the updated plan is available for other downstream processes.

    This is the default setting.

  2. Save Plan. This option is the same as the Save and Close Plan option except it does not close the plan. Since the plan is not closed, it is still using a managed server.

  3. Do Nothing. This option runs the Rapid Planning plan as scheduled but the plan is not saved and is still using a managed server.

Load Plan

Use this action to load a plan from the database to memory.

You must load a plan before you can view, update, or simulate it.

It displays a plan status page in a pop-up window. Use this page to monitor the progress of each phase of the load. You can close this page and do other work and the load process keeps running.

Release Plan

Use this action to perform releases, reschedules, and cancellations in the current selected plan.

You can release the plan if you have not loaded it into memory.

It opens a release plan page in a pop-up window and asks you to confirm the release.

After you confirm, it opens a plan status page in a pop-up window. Use this page to monitor the progress of each phase of the release. It displays the concurrent request numbers of the processes.

To see how to mark orders for release, see Rapid Planning Workbench Views > Supply & Demand > Releasing.

If you are releasing a simulation that has changes to these types of data, the release process releases the order but does not release the component or resource requirement details:

Save Plan

Use this action to save a plan from your workspace to the database.

It opens a save plan page in a pop-up window.

Field Plan shows the plan that you currently have selected and you can select another one instead.

Select a value for field Post-Save Options > Release recommendations:

Select a value for field Post-Save Options > Publish analytics to APCC:

After you confirm, it opens another save plan status page in a pop-up window. It displays the concurrent request number of the process.

Multiple Planners Working On the Same Plan

This is how Oracle Rapid Planning processes data when more than one planner is working on the same plan: