ProcedureTo Replace an SSC

Before You Begin

Before replacing, removing, or adding an SSC, be sure to deactivate all farms associated with that SSC. You can do so either from the Control Center or by running the farm -d farm-ID command from the N1 Provisioning Server command line.

Steps
  1. Before physically removing the SSC1, type removefru SSC1 from the power controller.

    See the Sun Fire B1600 Blade System Chassis documentation for details on how to use this command.

  2. Replace the physical component.

  3. Type the shelfsync command on the control plane server to synchronize the physical state of the chassis with the database. See Synchronizing the Physical and Database Environment for details.

  4. Type the switchsync command to synchronize the configuration of the switch with the configuration stored in the database for that switch.


Example 2–6 switchsync Command


bash-2.03# switchsync -d 50151
Bench configuring the switch...It may take some time...
done.
Loading switch configuration...
done.
bash-2.03#