N1 Grid Service Provisioning System 5.0 Installation Guide

ProcedureHow to Upgrade Remote Agents and Local Distributors

If you are running Remote Agents and Local Distributors on an operating system version that is not supported by the N1 Grid Service Provisioning System 5.0, you first upgrade the server to an operating system that is supported by both the 4.1 and 5.0 versions of the N1 Grid Service Provisioning System. Then, you use the browser interface to upgrade all of the Remote Agents and Local Distributors in your network. After the applications have been upgraded, you can then upgrade your servers to numerically higher versions of the operating system, if they are supported by the N1 Grid Service Provisioning System 5.0.

For example, you are running a 4.1 Remote Agent on a Red Hat Linux 7.1 server and you want to upgrade that server to Red Hat Linux 3.0 Advanced Server. First, you need to upgrade the server to Red Hat Linux Advanced Server 2.1, which is supported by both the 4.1 and 5.0 versions of the N1 Grid Service Provisioning System. Second, upgrade all of the Remote Agents by using the browser interface to the Master Server. Finally, upgrade the server to Red Hat Linux 3.0.

Before You Begin

Migrate the Master Server before upgrading Remote Agents and Local Distributors.

Steps
  1. Identify any server that is running the 4.1 Remote Agent or Local Distributor on an operating system that is not supported by the N1 Grid Service Provisioning System 5.0.

    For a list of supported operating systems, see Supported Operating Systems.

  2. On each server that is running the 4.1 Remote Agent or Local Distributor on an operating system that is not supported by the N1 Grid Service Provisioning System 5.0, upgrade the operating system to a version that is supported by both the 4.1 and 5.0 versions of the N1 Grid Service Provisioning System.

  3. Log in to the browser interface of the N1 Grid Service Provisioning System 5.0 Master Server.

  4. Click Hosts.

  5. Click masterserver.

  6. Click the Update Entire N1 SPS network... button.

    A window opens and displays a list of hosts that are being upgraded. The progress of the upgrade is also displayed. When the process completes, the window displays the following message.


    Host Update not yet complete.
  7. Click the Close button.

  8. To complete the second phase of the upgrade, click the Update Entire N1 SPS network... button again.

    A window displays a list of hosts that are being upgraded. The progress of the upgrade is also displayed. When the process completes, the status for each of the hosts displays as Updated.

  9. Click the Close button.

    The upgrade is complete.

  10. Prepare the Hosts that you upgraded.

    Before you can run a Plan on a Host that you upgraded, you must Prepare the Host. To Prepare Hosts, follow the instructions in How to Prepare a Physical Host in N1 Grid Service Provisioning System 5.0 System Administration Guide .

  11. (Optional) If you want to upgrade the operating system on your servers to a numerically higher version, you may do so.

    The version to which you upgrade the operating system must be supported by the N1 Grid Service Provisioning System 5.0.