Configuring Java CAPS Business Processes

ProcedureTo bind a correlation set to an activity

  1. In the Business Process Designer, select an activity.

  2. On the Business Process Designer toolbar, click Show Property Sheet.

  3. Click in the Use Correlations field, and then click the ellipsis (...).

    The Use Correlations dialog box appears.

  4. Click Add.

    The Assign Correlation Set dialog box appears.

  5. In the Select From List panel, select the names of the correlation sets you want to bind to the activity, and then click Add.

  6. Click OK.

  7. On the Use Correlations dialog box, click OK.