Sun Java Communications Suite 5 Installation Guide

Calendar-Messaging Schema 1 Example

This example installs Calendar Server and Messaging Server in an LDAP Schema 1 environment on two hosts. A remote version of Directory Server is used.

Requirements

Both Calendar Server and Messaging Server require Directory Server, but not necessarily a local copy.

ProcedureTo Develop a Sequence for Host A

The following high-level tasks are required:

  1. Checking the installation sequence guidelines

    Check to see what guidelines apply to this example and make adjustments as needed.

  2. Checking the installation prerequisites

    Check to see what tasks you might need to perform for this installation before starting.

  3. Installing Directory Server and Directory Preparation Tool

  4. Running Directory Preparation Tool.

  5. Start Directory Server.

ProcedureTo Develop a Sequence for Host B

The following high-level tasks are required:

  1. Checking the installation sequence guidelines

    Check to see what guidelines apply to this example and make adjustments as needed.

  2. Checking the installation prerequisites

    Check to see what tasks you might need to perform for this installation before starting.

  3. Running the installer.

  4. At component selection, choosing Calendar Server and Messaging Server

    Directory Server and the Directory Preparation Tool are automatically selected.

  5. Deselecting Directory Server

    When you are prompted to choose a local or remote Directory Server, choose remote (the Directory Server that is already installed and running on Host A).

  6. Resolving incompatibilities

    The installer verifies software on your host and provides guidance if incompatibilities are identified.

  7. Selecting the Configure Now type

    You will receive a message that Calendar Server and Messaging Server cannot be configured during installation.

  8. Running the installation

  9. Viewing the Installation Summary and Log

  10. Completing any post-install configuration:

  11. Starting the product components in this order:

    1. Starting and Stopping Messaging Server

    2. Starting and Stopping Calendar Server