Sun N1 System Manager 1.3 Site Preparation Guide

Switch Considerations

Switch requirements are determined by the following factors:

The following worksheet can assist you in determining the total number of switch ports by type that you will need on your switch or switches.

Table 2–10 Switch Port Requirements Worksheet

Server Type 

10/100 Ports 

10/100/1000 Ports 

Management Server

   
 
  • Separate management network and provisioning network:

    Enter 1 in the 10/100 column.

    If you have not installed a third 1–Gbit NIC in the management server, enter 1 in the 10/100/1000 port column.

    If you have installed a third 1–Gbit NIC, enter 2 in the 10/100/1000 column.

  • Management network only:

    Enter 1 in the 10/100 column.

  • Provisioning network only:

    Enter 1 in the 10/100/1000 column.

Total: __________ 

Total: __________ 

 

RIS Server

   
 

Enter 1 in the 10/100/1000 column only if you have a provisioning network. 

   
 

Manageable Servers

   
 
  • Separate management, provisioning, and data networks:

    Total the number of manageable servers and enter that number in the 10/100 column

    Double the number of manageable servers and enter that number in the 10/100/1000 column.

  • Separate management network, and combined data and provisioning networks:

    Total the number of manageable servers and enter that number in the 10/100 column and in the 10/100/1000 column.

  • Combined management, provisioning, and data networks:

    Double the number of manageable servers and enter that number in the 10/100/1000 column.

  • Management network only:

    Total the number of manageable servers and enter that number in the 10/100 column only.

  • Provisioning network only:

    Total the number of manageable servers and enter that number in the 10/100/1000 column only.

Total: __________ 

Total: __________ 

       

10/100/100 connection for the corporate network: 

 

Total: 1 

       
 

Total the number of ports for each column: 

10/100 ports: 

10/100/1000 ports: 

 

Total: _________ 

Total: _________ 

Use the above totals to determine your switch requirements, and then connect the servers and switches according to your site plan.