This chapter covers the following topics:
This flow imports costs for all type of items using Open Interface import.
Open Interface
Cost_ImportProcess_OI
Not Applicable
Not Applicable
The following predefined data must be used:
| Entity | Field Name | Field Value | 
|---|---|---|
| User | User Name | MFG | 
| Responsibility | Responsibility | Manufacturing and Distribution Manager | 
| Organization | Inventory Organization | M1-Standard Costing Organization | 
The following data must be set up:
| Interface | Field Name | Field Value | 
|---|---|---|
| Define Cost Type | Cost Type | Pending | 
| Cost Type ID | 3 | 
Following are the details of the scenarios in the flow:
| Scenario | Objective | Artifact Method | Component Set | Main Component | 
|---|---|---|---|---|
| Item_Creation | This scenario creates an inventory item using an API | EGO_ITEM_PUB_PROCESS_ITEMS | EGO_ITEM_PUB_PROCESS_ITEMS_Main | |
| Organization_Assignment | This scenario assigns the item created above to the respective Organization | EGO_ITEM_PUB_PROCESS_ITEM_ORG_ASSIGNMENTS | EGO_ITEM_PUB_PROCESS_ITEM_ORG_ASSIGNMENTS_Main | |
| Cost_Import_Process | This scenario will import cost for the above item in the said Organization | COST_IMPORT_PROCESS_CSTPCIMP | COST_IMPORT_PROCESS_CSTPCIMP | |
| Cost_Inquiry | This scenario will inquire the cost for the above item in the said Organization | - | CST_COST_API_GET_ITEM_COST_Main | |
| Verification | - | VERIFICATION_COMPONENT |