Actual Cost of Work Performed (ACWP)
|
Actual cost incurred on work to date on an activity (task) or an entire
project. In PeopleSoft Program Management, the system determines this value
by using the cost analysis group that is defined for the project and summing
all actual amounts in that analysis group with an accounting date that occurs
on or before today's date.
|
|
Activity ID (activity identifier)
|
Unique identification code for an activity.
|
|
Actual Work
|
The actual number of hours that are spent by a labor resource on an
activity. Actual work is captured in the Project Activity Team table (PROJ_ACT_TEAM)
from hours recorded on PeopleSoft Expenses time reports. The system calculates
actual work at the activity level by rolling up the detailed actual rows.
|
|
As of Date
|
The last date for which a report or process includes data.
|
|
Business Unit
|
Identification code that represents a high-level organization of business
information. You can use a business unit to define regional or departmental
units within a larger organization.
|
|
Budgeted Cost of Work Performed (BCWP)
|
Also referred to as earned value, BCWP is the budgeted cost-based on
percent complete. BCWP is zero until work is started on an activity (that
is, when percent complete is no longer zero). The calculation is based on
percent complete, as compared with the activity's duration. To determine this
value within PeopleSoft Program Management, the system:
-
Determines the budget date as Activity
Start Date + (Duration × Percent
Complete ÷ 100)
-
Uses the budget analysis group on the Project Costing Definition
page and sums all budget amounts in that analysis group with an accounting
date that occurs after the activity start date and before or on the budget
date.
|
|
Budgeted Cost of Work Scheduled (BCWS)
|
The budgeted costs up to the end date of the specified time period.
Using the Budget Analysis group on the Project Costing Definition page, this
value is the sum of all budget amounts in that analysis group with an accounting
date that occurs on or after the activity start date and before or on the
end date of the specified period.
|
|
Cost Performance Index (CPI)
|
Ratio of work accomplished versus the cost of work incurred for a specified
time period. The CPI is an efficiency rating for work accomplished for the
resources expended.
|
|
Duration
|
Duration is the length of time that is needed to complete an activity.
More precisely, it is the number of business days between an activity's start
and end dates.
|
|
Effective Date
|
Date on which a table row becomes effective, or the date that an action
begins. For example, if you want to close out a ledger on June 30, the effective
date for the ledger closing is July 1. The effective date also determines
when you can view and change the information. Pages and batch processes that
use information with an effective date use the current row.
See "Using Effective Dates" in the PeopleTools
PeopleBook: Using PeopleSoft Applications.
|
|
EmplID (employee identification)
|
Unique identification code for an individual who is associated with
your organization.
|
|
Enterprise Program Tree
|
A hierarchical structure of projects and programs that are created and
managed using PeopleSoft Tree Manager. In this tree, the root node must be
a program, under which can contain multiple programs and detail projects.
You establish an enterprise program tree for each project business unit.
|
|
Estimate to Complete (ETC)
|
An estimate of the time or effort required to complete the activity.
Expressed in either dollars or hours.
|
|
Forecast
|
Estimates or predictions of conditions and events in the project's future
based on information and knowledge available at the time of the forecast.
In PeopleSoft Program Management, forecasts are used in two ways, estimate
at completion (EAC) and in the Services Forecasting feature.
EAC is the expected total cost of a schedule activity or project when
the defined scope of work will be completed. EAC is the sum of ACWP and ETC.
The EAC may be calculated based on performance to date or estimated by the
project team based on other factors.
Services Forecasting is a feature in PeopleSoft Program Management that
enables you to collect labor resource estimates of hours that they will spend
on a project or activity and compare them to budgeted hours and actual workforce
utilization.
|
|
Forecast Horizon
|
The period of time for which a resource is expected to forecast hours
at a detailed level. This is used only with the Services Forecasting feature.
|
|
Forecast Period
|
The frequency at which resources are expected to update and submit forecasted
hours. This is used only with the Services Forecasting feature.
|
|
Generic Resource
|
A resource that does not have an ID to which it is associated. This
could be a labor resource with no employee ID, an asset resource with no asset
ID, or a material resource with no item ID. You can identify a generic resource
by entering the name of the generic resource when you need to assign a resource
to an activity, but the specific employee, asset, or item has not yet been
identified.
|
|
Percent Complete
|
A measure of the progress or completeness of an activity or project.
These methods determine percent complete, depending on what is being measured:
-
Duration: ((Original Duration − Remaining
Duration) ÷ Original Duration) ×
100
-
Manual: entered manually.
-
Budget Hours: Actual Hours ÷ Budgeted
Hours × 100
-
Budget Amount: Actual Amount ÷ Budgeted
Amount × 100
-
Forecast Hours: Actual Hours ÷ Forecasted
Hours × 100
-
Forecast Amount: Actual
Amount ÷ Forecasted Amount ×
100
|
|
Process Frequency
|
Designates the appropriate frequency in the Process Frequency group
box:
Once executes the request the next time
the batch process runs. After the batch process runs, the process frequency
is automatically set to Don't Run.
Always executes the request every time the
batch process runs.
Don't Run ignores the request when the batch
process runs.
|
|
Program
|
A vehicle for grouping detail projects for the purpose of reporting
and management. A program cannot have activities or resources to which is
it directly associated .
|
|
Project
|
A vehicle for identifying an initiative that has a specified start and
end date. A project can be either a detail project, which allows for associated
activities and resources, or a program.
|
|
Project Charging Level
|
The specified level of the work breakdown structure (WBS) at which you
create budgets and capture costs for a project. The project charging level
can be WBS level 1, level 2, level 3, or all detail activities.
|
|
Project Request
|
A vehicle for officially requesting and justifying that the organization
expend funds and effort for a finite period of time. You can submit different
business case scenarios by entering multiple versions of a project request
into the system, however, only one version of a request can be approved.
|
|
Report ID
|
Unique report identifier.
|
|
Report Manager
|
This link accesses the Report List page, where you can view report content,
check the status of a report, and view content detail messages that show you
a description of the report and the distribution list.
|
|
Process Monitor
|
This link accesses the Process List page, where you can view the status
of submitted process requests.
|
|
Remaining Work
|
Remaining work, also known as estimate to complete (ETC). ETC = Work − Actual Work.
|
|
Run
|
This button accesses the Process Scheduler request page, where you can
specify the location where a process or job runs and the process output format.
|
|
Run Control ID
|
Identification code that identifies the run parameters for a report
or process.
|
|
Schedule Method
|
The concept of schedule method is important to keeping the relationship
between work, duration, and resources synchronized. Schedule method is an
activity-level field that indicates which variable in the formula (#
of Resources × Sum (Resource Effort) ÷ #
of Resources) × Duration = Work is
constant. Options are Fixed Work, Fixed
Duration, or Fixed Units.
|
|
Schedule Performance Index (SPI)
|
Ratio of work that is accomplished versus work that is planned for a
specified time period. The SPI is an efficiency rating for work accomplishment
that compares work accomplished to what should have been accomplished.
|
|
SetID
|
Identification code that represents a set of control table information
or tablesets. A tableset is a group of tables, which are also known as records,
that are necessary to define a company's structure and processing options.
|
|
Status
|
Indicates whether a row in a table is Active or Inactive. You
cannot display inactive rows on transaction pages or use them for running
batch processes. To maintain an audit trail, it is more prudent to deactivate
rather than delete data that you no longer use.
|
|
Time Report Charging Level
|
The specified level of the WBS at which you will capture time report
information in PeopleSoft Project Costing. The time report charging level
can be WBS level 1, level 2, level 3, or all detail activities, and can be
different than the project charging level.
|
|
User ID
|
The system identifier for the individual who generates a transaction.
|
|
Work
|
The total number of hours spent or to be spent by a resource on an activity.
Work does not equal duration. For example, the expected duration of an activity
can be five days, but the work assigned to the activity might be 80 hours
with two resources working on the activity. You define work in hours at the
activity level.
|
|
Work Breakdown Structure (WBS)
|
A visual representation of a project, typically in a hierarchical view
or Gantt chart view that shows project activities.
|