Controlling Project Changes

This chapter provides an overview of change control management and discusses how to:

Click to jump to parent topicUnderstanding Change Control Management

This section discusses:

Click to jump to top of pageClick to jump to parent topicChange Control Management

In PeopleSoft Program Management, you can enable change control for project, budget, and ETC changes. You can determine the depth of change control using one of these levels:

A change control template stores the level of control for attributes that are to be monitored. You assign a default template at the business unit level. When you enable change control on a project, this system populates the template that you assigned at the business unit level as the default, but you can override it by selecting a new template.

This table lists the attributes for which you can enable change control and the level of control available for each attribute:

Attribute

Change Request Required

User Input

On

Off

Project Level - Updating Project Dates

Yes

Yes

Yes

Yes

Project Level - Updating Project Status

Yes

Yes

Yes

Yes

Project Resource Level - Add and Delete Resource

Yes

Yes

Yes

Yes

Project Resource Level - Updating Resource Dates

Yes

Yes

Yes

Yes

Activity Level - Add and Delete Activities

Yes

Yes

Yes

Yes

Activity Level - Updating Activity Dates

Yes

Yes

Yes

Yes

Activity Level - Updating Activity Status

Yes

Yes

Yes

Yes

Activity Level - Change Milestones

Yes

Yes

Yes

Yes

Activity Resource Level - Add and Delete Resources

Yes

Yes

Yes

Yes

Activity Resource Level - Updating Resource Units

Yes

Yes

Yes

Yes

Transaction Level - Add and Delete Transactions

No

No

Yes

Yes

Estimate to Complete Level - Updating Estimate to Complete

Yes

No

Yes

Yes

Budget Plan Level - Finalize Budget Plan

Yes

Yes

Yes

Yes

When change control is enabled and you designate specific attributes in the template to have change control, the system stores a record of all the data changes to these attributes on the Change Control Information table (PC_CHC_INFO). If specified, the system requires the user who initiates the change to enter the reason for making a change or to create a formal change request that requires approval before the changes take place. After changes take place, you can view a summarized list of the changes and the details of each change.

These steps describe how to implement the change control management functionality:

  1. Use the Change Control Template page to create a change control template that defines the attributes to monitor, such as whether a formal change request is required or changes require a reason from the user who initiates the change.

    Once created, specify the default change control template for a projects business unit on the Program Management Options page.

  2. Enable change control and select a template at the project level by using the Program Management page.

    If the change control template you select specifies change control for attributes at the activity level, you can disable it for individual activities on the Activity - Definition page for the User Input and On levels. If you have change control at the project level set to Change Request Required, you cannot override this at the activity level.

  3. Make changes to the project, budget or ETC as necessary.

    As changes are made or approved, if a change request is required for any of the defined change control attributes, the system records the name of the user who is making the change, the change that is made, and the date for data changes in the PC_CHC_INFO table. You can view the changes on the Change Control Monitor page and Change Control Details page.

See Also

Defining Change Control Templates

Click to jump to top of pageClick to jump to parent topicChange Requests for Project and Budget Changes

Users can enter project and budget change requests in two ways:

If you enable change control for a project that requires change requests, the project must have a project manager. Similarly, if you enable change control for a budget plan that requires change requests, you must specify the budget approver on the Project General - Program Management page. Although, if the approver is the individual who is making the data change, the system accepts the change and does not require a formal change request.

This diagram illustrates the change control process for budget and project changes:

Change control flow diagram

Click to jump to top of pageClick to jump to parent topicChange Requests for ETC Changes

ETC defines remaining work for a resource on an activity. This field is first populated when a project manager enters assigned work for a resource on an activity. You may update this field by using the Time Reporting feature in PeopleSoft Expenses, and the value appears on the Resources by Activity page (PC_ARL) after the Expenses to Projects integration process (PC_EX_TO_PC) completes. The ETC change request functionality is available only if you use PeopleSoft Expenses.

The method of approving an ETC change request is based on:

This diagram illustrates the process flow for entering, submitting, and approving ETC change requests:

ETC change request process flow diagram

See Also

Preparing Time Reports and Time Adjustments

Click to jump to top of pageClick to jump to parent topicChange Requests for Cross-Project Dependencies

A cross-project dependency exists if you have an activity (successor) in one project that is dependent on an activity (predecessor) in another project. If you change the start date or end date of the predecessor activity that impacts the dates of the successor activity in a different project, the dates of the successor activity are not updated in real-time. The system automatically generates a change request to update the dates of the successor activity and routes the change request to the project manger of the project that contains that successor activity. The project manager has the opportunity to approve or decline the change request. If the project manager approves the change request, the system updates the successor activity dates. If the project manager declines the change request, the system does not update the activity dates and the dependency between the two activities is removed. Cross-project dependency change requests are like activity date change requests, except that they are generated by the system.

This graphic illustrates the cross-project dependency change request process flow:

Cross-project dependency change request process flow

See Also

Using Schedule Dependencies and Constraints

Click to jump to top of pageClick to jump to parent topicChange Request Approval Workflow

Project change requests require project manager approval and budget changes requests require approval by the budget approver before the system updates the data elements with the changes. When you save and submit a change request, the system triggers workflow. A worklist entry and email notification are sent to the approver to indicate that a change request is available for review.

This diagram illustrates the change request workflow process flow:

Change Request Workflow process flow diagram

See Also

Delivered Workflows for PeopleSoft Program Management

Click to jump to parent topicTracking Project Changes

This section discusses how to:

Click to jump to top of pageClick to jump to parent topicPages Used to Track Project Changes

Page Name

Definition Name

Navigation

Usage

Change Control User Input

PC_CHC_INPUT

You can access the Change Control User Input page through multiple navigation paths. This list presents four frequently used paths.

  • Program Management, Project Definitions, General Information, General Information

    Save changes to a field that is specified on the change control template as User Input.

  • Program Management, Project Definitions, Resources, Resources

    Save changes to a field that is specified on the change control template as User Input.

  • Program Management, Project Definitions, Resources, Resources by Activity

    Save changes to a field that is specified on the change control template as User Input.

  • Program Management, Activity Definitions, Project Activities, General Information

    Save changes to a field that is specified on the change control template as User Input.

Enter the required reason for change.

Project Change Request

PGM_PRJ_CHC_REQ

You can access the Project Change Request page through multiple navigation paths. This list presents four frequently used paths. The primary path appears first.

  • Program Management, Project Management, Project Change Request, Project Change Request

  • Program Management, Project Definitions, General Information, General Information

    Save changes to a field that is specified on the change control template as Change Request Required.

  • Program Management, Project Definitions, Resources, Resources by Activity

    Save changes to a field that is specified on the change control template as Change Request Required.

  • Program Management, Activity Definitions, Project Activities, General Information

    Save changes to a field that is specified on the change control template as Change Request Required.

Enter details regarding the change request including changes to the project, activity, project resource list, and activity resource list.

Project Change Request (comments)

PGM_PRJ_CHC_CMNTS

Click the comments icon from the Project Change Request page.

Enter any comments regarding the change request.

Project Change Request (approval)

PGM_PRJ_CHC_REQ

  • Program Management, Project Management, Project Change Request, Project Change Request

  • Worklist, Worklist, Worklist for <User ID>:<Resource>

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Project Change Request Wrklist work item.

  • Click Worklist from the PeopleSoft universal navigation header.

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Project Change Request Wrklist work item.

Approve, decline, or return the change request.

Note. You must be the project manager in order to access this approval page.

Click to jump to top of pageClick to jump to parent topicEntering User Input for Changes

Access the Change Control User Input page (save changes to a field that is specified on the change control template as User Input.).

The page appears whenever changes are made to an attribute that requires user input. User input is an option that is available for most attributes that are on the Change Control Template page.

Type of Change

Enter the type of change. The value that corresponds to the initiated change appears by default in this field. Users can overwrite the value in this field.

Justification for Change

Enter the reason for the change. This is a required field.

If multiple changes are made on the same page and require user input, the Change Control User Input page appears with a scroll area to accommodate entering data for each change.

Click to jump to top of pageClick to jump to parent topicEntering Project Changes

Access the Project Change Request page (Program Management, Project Management, Project Change Request, Project Change Request).

The business unit, project, and release come from the program or project for which you are entering the change request.

Change Request ID

Displays NEXT for new change requests. The system generates and displays a unique ID after you save the change request.

Request Status

Displays the current request status. Possible values are:

Pending: The request has been created, but not submitted.

Submitted: The request has been submitted and is awaiting review by the approver. The page is display-only in this state.

Returned: The approver returned the change request for rework.

Approved: The approver approved the request. The page is display-only in this state.

Declined: The approver declined the change request. The page is display-only in this state and is not available for rework.

Expand All

Click to expand all of the group boxes. This icon appears only if you specify that a change request is required for at least one attribute at the project resource, activity, or activity resource level on the change control template.

Collapse All

Click to collapse all of the group boxes. This icon appears only if you specify that a change request is required for at least one attribute at the project resource, activity, or activity resource level on the change control template.

Save for Later

Click to save this change request in pending status. Use this option if you have not completed the change request. You can continue to make changes to this change request until you save and submit it to the project manager for review.

Save and Submit

Click to save the change request and trigger workflow processing. The system sends a worklist entry to the project manager. There must be project manager to save and submit this change request. The change request status is now Submitted.

Change Request Details

Priority

Select High, Medium, or Low for the priority of this change request. The system displays the priority on the worklist item.

Requestor

Displays the name of the user who enters the change request.

Approver

Displays the name of the current program or project manager. The program or project manager is responsible for approving the change request. The system sends a worklist item to this user when you submit the change request.

Creation Date

Displays the date on which you created the request.

Assigned To

Enter the employee ID to which you want to assign this change request. This field is only for informational purposes.

Due Date

Enter the date by which this change request should be completed.

Estimated Days

Enter the number of days that you estimate that might be added to the project if the project changes occur as a result of this change request. This field is only for informational purposes.

Resolution Date

Displays the date on which the change request is resolved. A change request is considered resolved when the approver either approves or declines the request.

Root cause

Enter a description of the root cause that requires this change request. This field is only for informational purposes.

Root Cause Area

Select from the list of active root cause areas. Root cause areas are set up at the setID level.

See Defining Root Cause Areas.

Application Area Impacted and Application Impacted

Displays the application area that is impacted and application impacted values from the program or project.

Project Request ID

Displays the project request ID. This value appears only if this project originated from a project request and the project is on the enterprise program tree.

See Establishing and Maintaining Enterprise Program Trees.

Request Type

Displays the initiative type ID description from the Project Request page. This value appears only if this project originated from a project request.

Risk Factor

Enter a number between 1 and 99 to indicate the relative risk of this change request. The application does not use this field for any processing.

Additional Fields

Click to transfer to a secondary page with ten additional user fields. The system does not use these fields for any processing or reporting, so you can enter any additional information for this change request.

Business Impact

Enter data about the potential impact of this change.

Financial Impact

Enter a numeric value and corresponding currency code to indicate the financial impact of this change

Date

Enter a date. This application does not use this field for any processing.

Project Changes

Old Project Status, Old Start Date, and Old End Date

Displays current values from the program or project.

New Project Status

Enter the new project status that you are requesting. This field prompts from the available active project statuses.

New Start Date

Enter the new start date that you are requesting. If you enter a new start date, you must also enter a new end date.

New End Date

Enter the new end date that you are requesting. If you enter a new end date, you must also enter a new start date.

Activity Changes

Enter and submit changes to project activities. The group box appears only if this is a project change request and a change request is required for at least one of the activity level attributes on the change control template. The system applies the changes only if the project manager approves the change request.

Action

Select the action to describe your change request from these options:

1 - Add: The system creates a new activity based on the data you enter and adds it to the project. This action appears only if you specify that a change request is required to add or delete activities on the change control template.

2 - Edit: The system changes the activity data based on the changes you enter for this row. This action appears only if you specify that a change request is required for updating activity dates, activity status, or changing milestones on the control template.

3 - Delete: The system deletes this activity from the project. This action appears only if the project's status is pending and you specify that a change request is required to add or delete activities on the change control template.

Activity

Enter the activity for which you want to request a change. If you select the Edit or Delete actions, you can use the prompt to select from a list of all activities that are associated with this project. If you select the Add action, the text NEXT appears and the system generates a new unique ID when the project manager approves this change request.

Description

Displays the description for the activity. If you select the Add action, you must enter a description for the activity.

Old Status

Displays the current activity status. If you are adding a new activity, the old status is blank.

New Status

Enter the new activity status. The system creates this activity status with the current effective date.

Status Description

Displays the description of the new status.

Old Start Date and Old End Date

Displays current dates from the activity for this resource. If you are adding a resource, these fields are blank.

New Start Date

Enter the new start date for this activity. If you enter a new start date, you must also enter a new end date.

Note. For summary activities, you can only change activity dates if the project's activity date cascade calculation is set to Manual Entry on the Project - Program Management page.

New End Date

Enter the new end date for this activity. If you enter a new end date, you must enter a new start date.

Old Milestone

Displays the current milestone flag value from the activity. If you add a new activity, this field is blank.

New Milestone

Select to indicate that this activity is a new milestone.

Click the comments icon to transfer you to the Project Change Request (comments) page on which you can enter any comments regarding this change request.

Project Resource List Changes

Enter and submit changes to the list of resources on the Resources page. The group box appears only if this is a project change request and a change request is required for at least one of the project resource level attributes on the change control template. The system applies the changes only if the project manager approves the change request.

Note. Project Resource List Changes apply only to labor resources.

Action

Select the action to describe your change request from these options:

1 - Add: The system adds a new resource based on the data you enter and adds it to the project. This action appears only if you specify that a change request is required to add and delete resources for the project resource level on the change control template.

2 - Edit: The system changes the activity data based on the changes you enter for this row. This action appears only if you specify that a change request is required for updating resource dates on the control template.

3 - Delete: The system deletes this resource or the schedule row from the project. If you leave the Schedule Number field blank, the system deletes the resource from the project. If you enter a value in the Schedule Number field, the system deletes the row from the project with the schedule number that you specify. This action appears only if you specify that a change request is required to add and delete resources for the project resource level on the change control template.

Resource Name

Displays the name of the resource who is associated with the ID you enter in the ID Number field. If you add a generic resource, you must enter a resource name.

ID Number

Enter the employee ID for which you are entering this change request. If you add a generic resource, you must use the text Generic. If you edit or delete a resource, the system prompts from the list of resources who are currently assigned to this project.

Schedule Number

Displays the schedule number for the resource. The system obtains the schedule number from the Resource Detail page. If you add a resource, this field is blank. The system assigns the schedule number when the project manager approves the change request.

If you edit or delete the resource, you can select the schedule that you want to edit or delete. The system obtains the prompt values for schedule numbers from the PROJ_TEAM_SCHED record for the resource. If you don't modify the schedule number, the system will only update the dates. If you enter a schedule number that does not exist, the system adds a new schedule for this resource.

Project Role

Enter the resource's project role. If you are adding this resource, you must enter a project role. If you are editing this resource's data, the current project role displays. You can enter a new project role for this resource. If you are deleting a resource, the resource's current project role appears.

Old Start Date and Old End Date

Displays current dates for the resource and schedule number that you select. If you add a resource, these fields are blank.

New Start Date and New End Date

Enter the new start and end dates for this resource and schedule number. If you delete a resource, you cannot enter dates into these fields.

Activity Resource List Changes

Enter and submit changes to the list of labor resources for an activity on the Resources by Activity page. The group box appears only if this is a project change request and a change request is required for at least one of the activity resource level attributes on the change control template. The system applies the changes only if the project manager approves the change request.

Note. Activity Resource List Changes apply only to labor resources.

Action

Select the action to describe your change request from these options:

1 - Add: The system adds a new resource to the activity based on the data you enter and adds it to the project. This action appears only if you specify that a change request is required to add and delete resources for the activity resource level on the change control template.

2 - Edit: The system changes the activity data based on the changes you enter for this row. This action appears only if you specify that a change request is required for updating resource units on the control template.

3 - Delete: The system deletes this resource from the activity. This action appears only if you specify that a change request is required to add and delete resources for the activity resource level on the change control template.

Activity ID

Enter the activity ID for which you want to add, edit, or delete a resource. You can select from activities that are associated with the project for which you are entering this change request.

Resource Name

Displays the name of the resource for the corresponding employee ID in the ID Number field. If you add a generic resource, you must enter a resource name.

Note. If you add a new resource to an activity and that resource is not on the project team, the system adds that resource to the project team when the project manager approves the change request. The system sets the Units field on the Resource Detail page to 100 percent.

ID Number

Enter the employee ID for the resource for which you are entering the change request.

If you select the 1 - Add action, Generic appears in this field. You can either add a generic resource or select from a list of all employee IDs. If you add a generic resource, you must enter a resource name.

If you edit or delete a resource, you can select from a list of resources that are currently assigned to the activity that you selected in the Activity field.

Old Units (%) (old units percentage)

Displays the current units percentage for the resource that you selected. If you are adding a resource, this field is blank.

New Units (%) (new units percentage)

Enter the value to specify the percentage time, based on the project calendar, for which the resource would be allocated to this activity schedule.

Click to jump to top of pageClick to jump to parent topicApproving Project Changes

Access the Project Change Request approval page (Program Management, Project Management, Project Change Request, Project Change Request).

The Project Change Request approval page is very similar to the Project Change Request page, although much of the approval page is display-only. You must be the project manager to access this approval page. This section highlights the differences on the approval page.

Date Submitted

Displays the date the change request was submitted for review.

Approver Comments

Enter any comments that explain the action you perform for this change request. If you decline this change request, the systems sends an email notification to the requestor that includes the approver comments.

Approve

Click to approve all items on the change request. The system updates the data with the requested changes. The status of the change request changes from Submitted to Approved.

Decline

Click to reject this change request. The system does not make any of the requested changes. If the change is caused by a cross-project dependency, the activity dependency between the two projects is broken. The status of the change request changes from Submitted to Declined.

Return

Click to return the change request back to the requestor for rework. The status of the change request changes from Submitted to Returned.

Note. This button does not appear if the change request originated from a cross-project dependency. If you do not want to approve the change request, you must decline the change request to break the dependency and the requestor can open a new request if desired.

Click to jump to parent topicTracking ETC Changes

This section discusses how to:

Click to jump to top of pageClick to jump to parent topicPage Used to Track ETC Changes

Page Name

Definition Name

Navigation

Usage

Time Report - General Time Report Information

TE_TIME_MAIN

  • Employee Self-Service, Travel and Expense Center, Time Report, Create, Create Time Report

  • Click the General Report Information link on the Time Report - Time Report Summary page.

Create a time report.

Approve Time Report - Time Report Summary

TE_TIME_LINES

Manager Self-Service, Travel and Expense Center, Approvals, Approve Transactions, Time Reports

Review and approve, hold, or deny time reports.

Note. You must be a time report approver or project manager to access this page.

Project Change Request (approval)

PGM_ETC_CHC_REQ

  • Program Management, Project Management, Project Change Request, Project Change Request

  • Worklist, Worklist, Worklist for <User ID>:<Resource>

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Project Change Request Wrklist work item.

  • Click Worklist from the PeopleSoft universal navigation header.

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Project Change Request Wrklist work item.

Approve or decline the change request.

Note. You must be the project manager in order to access this approval page.

Click to jump to top of pageClick to jump to parent topicEntering ETC Changes

Access the Time Report - General Time Report Information page (Employee Self-Service, Travel and Expense Center, Time Report, Create, Create Time Report).

Use this page, if you are a resource, to log time and optionally update the work you have remaining on an activity.

Enter the new remaining hours to complete in the New Estimate field and submit to trigger ETC change request processing. This field is available only if change requests are required for ETC changes on the change control template and the Allow Entry of Estimate to Complete check box is selected in the Expenses Definition - Business Unit 2 page.

See Configuring Business Units for PeopleSoft Expenses.

Click to jump to top of pageClick to jump to parent topicSubmitting and Approving ETC Changes

Access the Approve Time Report - Time Report Summary page (Manager Self-Service, Travel and Expense Center, Approvals, Approve Transactions, Time Reports).

Use this page if you are a resource supervisor or project manager to approve time reports and submit change requests.

New Estimate

Displays the new remaining work estimate that the resource entered. Project managers can update this field only if the PeopleSoft Expenses installation option indicates that project manager approvals are active and you are the project manager of the project for which the resource logged time.

Change Requests

Determines if the requirements have been met for a change request. The system automatically sets this field. This field behaves differently based on your role.

  • If you are the project manager and the PeopleSoft Expenses installation option indicates that project manager approvals are active, you can update this field.

    Select the check box to indicate that you approve the new estimate. The system generates a formal change request and approves it automatically.

    deselect the check box to indicate that you decline the change request and the system does not create a formal change request. If you do not deselect this check box, the system automatically creates and approves the change request and updates the remaining work for this resource on the activity specified.

  • If you are a human resources manager-supervisor, the system automatically selects this field when a change request is required. After you save, the system generates a formal change request and sends a worklist entry and email notification to the project manager.

Click to jump to top of pageClick to jump to parent topicApproving Formal ETC Change Requests

Access the Change Request approval page (Program Management, Project Management, Project Change Request, Project Change Request).

You use Project Change Request approval page to approve ETC changes. You must be the project manager to access this approval page. This section highlights the difference in the Project Change Request approval page for auto-generated ETC change requests.

Requestor

Displays the employee ID for the individual that created the time report.

Priority

Displays the priority. All ETC change requests are high priority.

Time Report ID

Displays the time report ID from which this change request was triggered.

Period End Date

Displays the time report end date from which this change request was triggered.

Change Explanation

Displays the text Estimate to Complete Change.

Estimate to Complete Changes

Activity ID

Displays the activity ID for which the user entered the ETC changes.

Start Date and End Date

Displays the start and end dates for the activity.

Actual Work

Displays the actual work hours that have been completed to date by the resource on this activity. This includes the hours that were recorded on the current time report.

Old Work

Displays the total for the activity's planned work for that resource. This field does not take into account the ETC changes that were recorded in this change request.

Old Remaining Work

Displays the total remaining work, which is calculated as (Old Work − Actual Work) before taking into account any change to the ETC change request.

New Work

Displays the new planned work for the resource on that activity if you approve the change request. For example, if the Old Work for a resource on an activity is 100 hours and there is an ETC change request that increases the amount of work remaining to be 20 more hours, the New Work value would be 120 hours.

New Remaining Work

Displays the total work that remains on the activity for the resource if you approve the ETC change request. The New Remaining Work value is the same value as the New Estimate value of the resource who appears on the time report.

Click to jump to parent topicTracking Changes to Cross-Project Dependencies

This section discusses how to approve changes to cross-project dependencies.

Click to jump to top of pageClick to jump to parent topicPage Used to Approve Cross-Project Dependencies

Page Name

Definition Name

Navigation

Usage

Project Change Request (approval)

PGM_PRJ_CHC_REQ

  • Program Management, Project Management, Project Change Request, Project Change Request

  • Worklist, Worklist, Worklist for <User ID>:<Resource>

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Project Change Request Wrklist work item.

  • Click Worklist from the PeopleSoft universal navigation header.

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Project Change Request Wrklist work item.

Approve or decline the change request.

Note. You must be the project manager of the project that contains the successor activity to access this approval page.

Click to jump to top of pageClick to jump to parent topicApproving Changes to Cross-Project Dependencies

Access the Project Change Request (approval) page (Program Management, Project Management, Project Change Request, Project Change Request).

This section highlights the differences in the Project Change Request approval page for auto-generated cross-project dependencies.

Requested By

Displays the name of the resource that changed the predecessor activity date.

Approver

Displays the project manager for the project to which the dependent activity belongs.

Change Explanation

Displays the text Cross Project Dependency Change from <Business Unit>, <Project>, <Activity> where the business unit, project, and activity values come from the activity that triggered this change request.

Click to jump to parent topicTracking Budget Changes

This section discusses how to:

Click to jump to top of pageClick to jump to parent topicPages Used to Track Budget Changes

Page Name

Definition Name

Navigation

Usage

Budget Change Request

PGM_BGT_CHC_REQ

  • Program Management, Project Management, Budget Change Request, Budget Change Request

  • Project Costing, Budgeting, Budget Plan, Budget Plan

    Click the Finalize button on the Finalize tab for a previously finalized budget row.

Enter details regarding the change request and the cost and revenue budget changes to request.

Budget Change Request (approval)

PGM_BGT_CHC_REQ

  • Program Management, Project Management, Budget Change Request, Budget Change Request

  • Worklist, Worklist, Worklist for <User ID>:<Resource>

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Budget Change Request Worklist work item.

  • Click Worklist from the PeopleSoft universal navigation header.

    Click the link that displays the concatenation of the business unit, project ID, and change request ID for a Budget Change Request Worklist work item.

Approve, decline, or return the change request.

Note. You must be the budget approver to access this approval page.

Click to jump to top of pageClick to jump to parent topicEntering Budget Changes

Access the Budget Change Request page (Program Management, Project Management, Budget Change Request, Budget Change Request).

The Budget Change Request page behaves in much the same way as the Project Change Request page. These sections highlight the differences on this page.

Save and Submit

Click to save the change request and trigger workflow processing. The system sends a worklist entry to the budget approver. A budget approver must exist on the Project General - Program Management page to save and submit this change request. After you click this button, the system changes to change request status to Submitted.

Project Request Details

The Project Request Details group box behaves in much the same way on this page as it does on the Project Change Request page. This section highlights the differences on this page.

Approver

Displays the budget approver that is specified on the Project - Program Management page. You must have a budget approver to submit this change request.

Request Type

Displays Budget as the type of change request.

Cost Budget Change

Enter any changes to a finalized cost budget.

Old Budget Plan

Displays the existing active cost budget from the most current finalized cost budget plan. The system also displays the description that appears as a link to the Budget Details page and the total amount of this cost budget plan. The amount, which is displayed in the base currency of the business unit, is the sum of the budget amounts from the Budget Summary record (PC_BUD_SUMMARY) for the given business unit, project ID, budget ID for cost budget types.

New Budget Plan

Enter the new cost budget plan to submit to the budget approver. The system also displays the description, that appears as a link to the Budget Details page, and the total amount of this cost budget plan. The amount is the sum of the budget amounts from the Budget Summary record (PC_BUD_SUMMARY) for the given business unit, project ID, budget ID for cost budget types.

Variance

Displays the difference between the old budget plan amount and the new budget plan amount in the new budget plan's currency.

Revenue Budget Change

Enter any changes to a finalized revenue budget.

Old Budget Plan

Displays the existing active revenue budget from the most current finalized revenue budget plan. The system also displays the description that appears as a link to the Budget Details page and the total amount of this revenue budget plan. The amount, which is displayed in the base currency of the business unit, is the sum of the budget amounts from the Budget Summary record for the given business unit, project ID, budget ID for revenue budget types.

New Budget Plan

Enter the new cost revenue plan to submit to the budget approver. The system also displays the description that appears as a link to the Budget Details page and the total amount of this revenue budget plan. The amount is the sum of the budget amounts from the Budget Summary record for the given business unit, project ID, budget ID for revenue budget types.

Variance

Displays the difference between the old budget plan amount and the new budget plan amount in the new budget plan's currency.

Click to jump to top of pageClick to jump to parent topicApproving Budget Changes

Access the Budget Change Request (approval) page (Program Management, Project Management, Budget Change Request, Budget Change Request).

The Budget Change Request approval page is very similar to the Budget Change Request page, although much of the approval page is display-only. You must be the budget approver to access this approval page. This section highlights the changes for the approval page.

Date Submitted

Displays the date on which the change request was submitted for review.

Approver Comments

Enter any comments explaining the action you perform for this change request. If you decline this change request, the systems sends an email notification to the requestor that includes the approver comments.

Approve

Click to approve all items on the change request. The system enables the Finalize button on the Budget Plan page to allow the user to finalize the newly approved budget plan. The status of the change request changes from Submitted to Approved.

Decline

Click to reject this change request. The system does not make any of the changes requested. The status of the change request changes from Submitted to Declined.

Return

Click to return the change request back to the requestor for rework. The status of the change request changes from Submitted to Returned.

Click to jump to parent topicViewing and Analyzing Changes

This section discusses how to:

Click to jump to top of pageClick to jump to parent topicPages Used to Enter and Analyze Changes

Page Name

Definition Name

Navigation

Usage

Change Control Monitor

PC_CHC_MONITOR

Program Management, Project Management, Change Control Monitor, Monitor

View a list of changes that occur for projects, budgets, and estimates to complete for which change control is enabled.

Change Control Details

PC_CHC_INFO

  • Program Management, Project Management, Change Control Monitor, Details

  • Program Management, Project Management, Change Control Monitor, Monitor

    Click the Change Control Details icon.

View details of a change, including comments that are entered on the Change Control User Input page. You can also add additional comments regarding the change.

Change Control Analysis

PC_EA_CHG_CONTROL

Program Management, Interactive Reports, Change Control

Use search criteria to display a list of changes in the scope of a project.

Click to jump to top of pageClick to jump to parent topicViewing Changes to a Project

Access the Change Control Monitor page (Program Management, Project Management, Change Control Monitor, Monitor).

This page lists a summary of changes to the specified change control attributes for a project.

Click the corresponding Change Control Details icon to view the details of that change.

Note. The change control option to monitor changes to resource dates does not show the net change to a resource's schedule if the resource has multiple schedules and only one schedule line was modified. This page displays a change in start date or end date on one schedule line at a time. The system also only checks for date changes; it does not track changes when you delete a schedule line.

Click to jump to top of pageClick to jump to parent topicViewing Change Details

Access the Change Control Details page (Program Management, Project Management, Change Control Monitor, Details).

This page displays the details of a change and includes user input if it was required. The Justification for Change and Comment History fields cannot be edited, but users can enter additional information in the Comments field. Click the Add Comments button to move text from the Comments field to the Comment History field, where the text appears with the date of input and the user ID who enters the comment.

Click to jump to top of pageClick to jump to parent topicAnalyzing Change Control

Access the Change Control Analysis page (Program Management, Interactive Reports, Change Control).

Enter the necessary search criteria to filter the results to display the projects that have change control data. Click the Search button to retrieve and display a list of projects that meet the specified parameters. Click the Reset button to reinstate the default search settings.

Change Control Metrics

Project

Click a project name link to access the project's Change Control Monitor page.

Number of Changes

Displays the total number of changes that are recorded for the project.

Number Scope Changes

Displays the number of change control rows for the project for which the type of change is Scope.

Days Added/Reduced

Displays the total number of days by which the project is increased or decreased, based on change control rows for project date changes.

Team Members Added

Displays the number of team members who are added to the project.

Team Members Reduced

Displays the number of team members who are removed from the project.