Configuring a Disaster-Recovery environment requires these steps:
Install and configure EPM System at the production site.
Runtime executables and data should be on a replicatable partition
Distributed services must be clustered to form a logical service.
If the host names at the standby site differ from the host names at the production site, set up host name aliases at the standby site. See Host Name Requirements.
When the EPM System configuration at the production site is complete, install and configure EPM System at the standby site.
Set up database replication.
Note: | You can use a backup and restoration procedure for replication. |
Enable the standby site.
Disable mirroring between the production and standby sites.
Run the crash-recovery procedure for each application to recover Essbase. See Chapter 4, Essbase Components, in the Oracle Hyperion Enterprise Performance Management System Backup and Recovery Guide.
Start the services on the standby hosts.