You can roll up the data from a worksheet column into a project or shell cost sheet or cost template column.
To add a worksheet column to the cost sheet
1 | In the cost sheet, click Columns, then click New. The Column Properties window opens. |
2 | Complete the window: |
• | In the Datasource column, choose any of the Project Cost datasources Project Cost 1 through Project Cost 25. |
• | For Entry Method, choose Worksheet. |
• | Choose the worksheet (name), then the column within the worksheet. |
3 | Complete the rest of the Column Properties window and click OK. |
Oracle Corporation
Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.