Working with Generic Cost Business Processes

The Generic Cost Manager can use Generic Cost BPs as datasources. These BPs are created in Primavera uDesigner. These Generic Cost BPs work only with the Generic Cost Manager, and also only in the context of a shell. The possible Generic Cost BP types are:

Generic: Reference against company-level commit; enforce against company-level commit amount.
Transfer: Transfer value from one cost code to another
Base Commit: Creates an entry in the Commitment Summary. Works in conjunction with Change Commit and General Spends Generic Cost BPs. Reference against company-level commit; enforce against company-level commit amount.
Change Commit: Works in conjunction with Base Commit and General Spends Generic Cost BPs. Updates the Commitment Summary. Reference against company-level commit; enforce against company-level commit amount.
General Spends: Works in conjunction with Base Commit and Change Commit Generic Cost BPs.Updates the Commitment Summary.
Lease: Works in a shell to manage lease payments and payment history.

Step 1: Import Generic Cost BPs. You import, configure and set up the Generic Cost BPs in the same manner as all other BPs.

Step 2: Set up the Commitment Summary template. See "Setting up the Commitment Summary Template".

 

 

 

 


Oracle Corporation

Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.