Create a gates setup

You can create a gates setup in project templates, and in individual projects. There can be one setup per project.

To create a new gates setup

1 Go to the Company Workspace tab and switch to Admin mode.
1 Do one of the following:
To create the setup in a project template, click Templates > Projects (Standard) in the left Navigator. Open the project template.
To create the setup in a project, click Company Sponsored Projects in the left Navigator. Open the project.
2 Click Setup > Gates. The Gates Setup log opens.
3 Click New. The gate setup is created automatically. Double-click the setup, or select from the list and click Open. The Gates Setup window opens. There are three tabs: General, Settings, Schedule.
4 In the General tab, enter a Setup Name, which displays in the log, and an optional Description. At this point, Status is Inactive by default.
5 In the Settings tab, define project phases and gates conditions. For details, see "Add project phases to the gates setup (Settings tab)" and "Configure gate elements".
6 In the Schedule tab, you can schedule regular gates. See "Define gates runs schedule (Schedule tab)".

 

 

 

 