Set up the Resource Manager in a project or Shell template

In a project or shell template, you can set up the Resource Manager as you would within a project or shell. You can also set up a project/shell level resource allocation sheet if the Resource Manager configuration is set to allow allocations at the project/shell level.

To set up the Resource Manager in a project template

1 Go to the Company Workspace tab and switch to Admin mode.
2 Click Templates in the left Navigator.
For a project, click Projects (Standard) > [project].
For a shell, click Shells > [shell].

Primavera Unifier displays the Template Log in the right pane.

3 Double-click the name of the template in which you want to set up the Resource Manager.
4 In the Navigator, click Setup > Resource Manager.
5 On the right pane, select Resource Manager and click Open. The Configuration window opens.Complete the window as described in the table in "Set up the Resource Manager in a project/shell".
6 Complete the window as described in the table in "Set up the Resource Manager in a project/shell".
7 Click OK.

To set up a resource allocation sheet in a project/shell template

1 Go to the Company Workspace tab and switch to Admin mode.
2 Click Templates in the left Navigator.
For a project, click Projects (Standard) > [project].
For a shell, click Shells > [shell].

Primavera Unifier displays the Template Log in the right pane.

3 Double-click the name of the template in which you want to set up the allocation sheet.
4 In the Navigator, click Resource Manager > Resource Sheets.
5 On the right pane, double-click the Resource Allocation sheet. The Resource Allocation sheet opens.

Primavera Unifier automatically creates an allocation sheet when the Resource Manager is activated in the project/shell.

6 To add resource allocations to the template, click the Add button. The Resource Allocation window opens.
7 Complete the window:
Role Name: Click Select, choose a role, and click OK.
Date From: Click the calendar and choose the start date for the allocation.
Date To: Click the calendar and choose the end date for the allocation.
Allocated Hours: Primavera Unifier automatically calculates the allocated hours and displays them in this field. You can edit the hours, if necessary.
8 Click OK.

 

 

 

 