Before you can link project or shell schedule sheets to a template for updating, you must enable the template for linking.
To enable linking for a schedule sheet template
1 | Go to the Company Workspace tab and switch to Admin mode. |
2 | Click Templates in the left Navigator. |
• | For a project template, in the left Navigator, click Templates > Projects (Standard) > [project] > [project template] > Schedule Manager > Schedule Sheets. |
• | For a shell template, in the left Navigator, click Templates > Shells > [shell type] > [shell template] > Schedule Manager > Schedule Sheets. |
3 | On the Schedule Sheets log, select a Schedule Sheet template. |
4 | From the Edit menu, select Sheet Linking > Enable. |
To disable linking for a schedule sheet template
1 | On the Schedule Sheets log, select a Schedule Sheet template. |
2 | From the Edit menu, select Sheet Linking > Disable. |
Disabling Sheet Linking disconnects all project/shell schedule sheets from the linked template; the schedule sheets can no longer receive updates from the template.