Setting up Scope Management for Activities
After you create the project- or shell-level schedule sheet template at the company level, you can set up the following for each activity:
|
•
|
Responsible users or groups |
To set up Scope Management for an activity
|
1
|
Go to the Company Workspace tab and switch to Admin mode. |
|
2
|
Click Templates in the left Navigator. |
|
•
|
For a project template, in the left Navigator, click Templates > Projects (Standard) > [project] > [project template] > Schedule Manager > Schedule Sheets. |
|
•
|
For a shell template, in the left Navigator, click Templates > Shells > [shell type] > [shell template] > Schedule Manager > Schedule Sheets. |
The Schedule Sheets log opens.
|
3
|
Select the template from the log and click the Open button, or double-click the selected template. The schedule sheet template opens. |
|
4
|
To set up scope management for the template, use the instructions in the Unifier Users Guide on setting up scope management for activities. |