About Calendars and Activities

When you select or change an activity calendar, the calendar affects the following dates and date pickers:

Start Date date picker
Finish Date date picker
Duration calculation
Actual Start Date date picker
Actual Finish Date date picker
Actual Duration
Forecast Start calculation
Forecast Finish calculation
Forecast Duration calculation
Critical Path
Estimate dates
Estimate duration
Float calculation
Progress window Progress As Of Date date picker
Budget and Progress options Do not allow progress entry older than the current period and Allow editing of last progress
Any date or date only picker data element

This is how the dates are changed when the activity calendar changes. Changes occur when the schedule sheet is refreshed.

Activity (not started): If the Start Date is affected by a new activity calendar, the Start Date and Finish Date will change to keep the Duration as specified. The system will use the next day on the calendar.
Activity (not started): If the Finish Date is affected by a new activity calendar, the system will select either a previous or next working day on the calendar.
Activity (in progress): If the Finish Date is affected by a new activity calendar, the system will select either a previous or next working day on the calendar. The Start Date is not affected in this case.
Activity (completed): No impact on Start Date or Finish Date for the activity.

 

 

 

 


Oracle Corporation

Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.

Copyright Information