About Calendars and Activities
When you select or change an activity calendar, the calendar affects the following dates and date pickers:
|
•
|
Finish Date date picker |
|
•
|
Actual Start Date date picker |
|
•
|
Actual Finish Date date picker |
|
•
|
Forecast Start calculation |
|
•
|
Forecast Finish calculation |
|
•
|
Forecast Duration calculation |
|
•
|
Progress window Progress As Of Date date picker |
|
•
|
Budget and Progress options Do not allow progress entry older than the current period and Allow editing of last progress |
|
•
|
Any date or date only picker data element |
This is how the dates are changed when the activity calendar changes. Changes occur when the schedule sheet is refreshed.
|
•
|
Activity (not started): If the Start Date is affected by a new activity calendar, the Start Date and Finish Date will change to keep the Duration as specified. The system will use the next day on the calendar. |
|
•
|
Activity (not started): If the Finish Date is affected by a new activity calendar, the system will select either a previous or next working day on the calendar. |
|
•
|
Activity (in progress): If the Finish Date is affected by a new activity calendar, the system will select either a previous or next working day on the calendar. The Start Date is not affected in this case. |
|
•
|
Activity (completed): No impact on Start Date or Finish Date for the activity. |