This section contains scenarios based on the option selected for % Complete Calculation Method being Lead resource updates Activity and other resources. There is only one data entry scenario for this setting.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Activity and resource % complete updates % earned |
• | % Complete Calculation Method option = Lead resource updates Activity and other resources |
• | % Earned Calculation Method option = Lead resource updates Activity and other resources |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered |
Earned Progress |
Calculated (read-only) Same as Activity % Complete |
|
Resource |
||
|
Progress Quantity |
Manual entry. (Only resource that is selected under dropdown). For all other resources, Progress Quantity will be calculated based on (Leader Progress Quantity / Leader Quantity) * Resource Quantity |
Earned Progress |
Calculated (read-only) Same as Progress Quantity |