Method is Manual activity % complete - updates resource % complete

This section contains scenarios based on the option selected for % Complete Calculation Method being Manual activity % complete - updates resource % complete.

% Earned Calculation Method option is Manual activity % earned and resource % earned

If the entry method and option settings on the Budget and Progress Method Setup window are:

% Complete and Earned Progress entry method = Independently Control % complete and earned quantity
% Complete Calculation Method option = Manual activity % complete - updates resource % complete
% Earned Calculation Method option = Manual activity % earned and resource % earned

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Manual entry

Earned Progress

Manual entry

Resource

 

Progress Quantity

Calculated (read-only).

(Activity-level Activity % Complete * Quantity)

Earned Progress

Manual entry

% Earned Calculation Method option is Manual activity % earned - updates resource % earned

If the entry method and option settings on the Budget and Progress Method Setup window are:

% Complete and Earned Progress entry method = Independently Control % complete and earned quantity
% Complete Calculation Method option = Manual activity % complete - updates resource % complete
% Earned Calculation Method option = Manual activity % earned - updates resource % earned

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Manual entry

Earned Progress

Manual entry

Resource

 

Progress Quantity

Calculated (read-only).

(Activity-level Activity % Complete * Quantity)

Earned Progress

Calculated (read-only).

(Activity-level Earned Progress * Quantity)

% Earned Calculation Method option is Resource updates Activity - weighted average of resource costs

If the entry method and option settings on the Budget and Progress Method Setup window are:

% Complete and Earned Progress entry method = Independently Control % complete and earned quantity
% Complete Calculation Method option = Manual activity % complete - updates resource % complete
% Earned Calculation Method option = Resource updates Activity - weighted average of resource costs

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Manual entry

Earned Progress

Calculated (Weighted Cost)

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

Resource

 

Progress Quantity

Calculated (read-only).

(Activity-level Activity % Complete * Quantity)

Earned Progress

Manual Entry

% Earned Calculation Method option is Lead resource updates Activity and other resources

This combination of settings is not available.

% Earned Calculation Method option is Update Activity and all resources on activity start and finish

If the entry method and option settings on the Budget and Progress Method Setup window are:

% Complete and Earned Progress entry method = Independently Control % complete and earned quantity
% Complete Calculation Method option = Manual activity % complete - updates resource % complete
% Earned Calculation Method option = Update Activity and all resources on activity start and finish

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Manual entry

Earned Progress

Calculated (Weighted Cost)

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

Resource

 

Progress Quantity

Calculated (read-only).

(Activity-level Activity % Complete * Quantity)

Earned Progress

Calculated based Update Activity and all resources on activity start and finish.

For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then,

when Actual Start is entered, Earned Progress = 5% * Quantity

When Actual Finish is entered, Earned Progress = 100% * Quantity.

 

 

 

 