This section contains scenarios based on the option selected for % Complete Calculation Method being Manual activity % complete and resource % complete. There is only one data entry scenario for this setting.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Activity and resource % complete updates % earned |
• | % Complete Calculation Method option = Manual activity % complete and resource % complete |
• | % Earned Calculation Method option = Not available |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Manual entry |
Earned Progress |
Calculated (read-only) Same as Activity % Complete |
|
Resource |
||
|
Progress Quantity |
Manual entry |
Earned Progress |
Calculated (read-only) Same as Progress Quantity |